Quotedata_finalizarii 11.09.2024 (TERMEN INITIAL FINALIZARE PROIECTARE) 19.06.2031 (CF AA NR. 4)Stie careva daca noul termen ST+PT listat pt Ploiesti-Brasov e cu adevarat corect? Adica chiar se ras-prelungeste contractul cu 7 ani peste cel care facea misto Grinda ca vai era de 5 ani?
Quote from: raulbogdan23 on May 10, 2024, 11:05:53 PMTunel Momaia
Data Fir 1 - SB-AG Fir 2 - AG-SB 03.10.2023 0m 0m 25.10.2023 necunoscut 0m 10.01.2024 142m 80m 15.02.2024 314m 195m 08.03.2024 414m 283m 15.03.2024 450m 307m 29.03.2024 491m 364m 30.04.2024 580m 430m 11.05.2024 625m 470m Ramas 725m 880m