România => Nivel național => Rutier => Topic started by: north on June 18, 2016, 02:58:29 AM

Title: Monthly Road Infrastructure Digest (EN)
Post by: north on June 18, 2016, 02:58:29 AM
May 2016: Motorways: plans and projects (http://forum.peundemerg.ro/index.php?topic=446.msg120530#msg120530)  *  A1 Bucharest - Nădlac (http://forum.peundemerg.ro/index.php?topic=446.msg120531#msg120531)  *  A3 Bucharest - Borș (http://forum.peundemerg.ro/index.php?topic=446.msg120532#msg120532)  *  A7 Ploiești - Bacău - Siret (http://forum.peundemerg.ro/index.php?topic=446.msg120533#msg120533)  *  A10 Sebeș - Turda (http://forum.peundemerg.ro/index.php?topic=446.msg120534#msg120534)  *  National roads (http://forum.peundemerg.ro/index.php?topic=446.msg120535#msg120535)  *  Bypasses (http://forum.peundemerg.ro/index.php?topic=446.msg120536#msg120536)

June 2016: Motorways: plans and projects (http://forum.peundemerg.ro/index.php?topic=446.msg121646#msg121646)  *  A1 Bucharest - Nădlac (http://forum.peundemerg.ro/index.php?topic=446.msg121647#msg121647)  *  A3 Bucharest - Borș (http://forum.peundemerg.ro/index.php?topic=446.msg121648#msg121648)  *  A7 Ploiești - Bacău - Siret (http://forum.peundemerg.ro/index.php?topic=446.msg121753#msg121753)  *  A10 Sebeș - Turda (http://forum.peundemerg.ro/index.php?topic=446.msg121754#msg121754)  *  National roads (http://forum.peundemerg.ro/index.php?topic=446.msg121755#msg121755)  *  Bypasses (http://forum.peundemerg.ro/index.php?topic=446.msg121756#msg121756)

July 2016: Motorways: plans and projects (http://forum.peundemerg.ro/index.php?topic=446.msg124869#msg124869)  *  A1 Bucharest - Nădlac (http://forum.peundemerg.ro/index.php?topic=446.msg124870#msg124870)  *  A3 Bucharest - Borș (http://forum.peundemerg.ro/index.php?topic=446.msg124871#msg124871)  *  A7 Ploiești - Bacău - Siret (http://forum.peundemerg.ro/index.php?topic=446.msg124872#msg124872)  *  A10 Sebeș - Turda (http://forum.peundemerg.ro/index.php?topic=446.msg124873#msg124873)  *  National roads (http://forum.peundemerg.ro/index.php?topic=446.msg124874#msg124874)  *  Bypasses (http://forum.peundemerg.ro/index.php?topic=446.msg124875#msg124875)

August 2016: Motorways: plans and projects (http://forum.peundemerg.ro/index.php?topic=446.msg127872#msg127872)  *  A1 Bucharest - Nădlac (http://forum.peundemerg.ro/index.php?topic=446.msg127873#msg127873)  *  A3 Bucharest - Borș (http://forum.peundemerg.ro/index.php?topic=446.msg127874#msg127874)  *  A7 Ploiești - Bacău - Siret (http://forum.peundemerg.ro/index.php?topic=446.msg127875#msg127875)  *  A10 Sebeș - Turda (http://forum.peundemerg.ro/index.php?topic=446.msg127876#msg127876)  *  National roads (http://forum.peundemerg.ro/index.php?topic=446.msg127877#msg127877)  *  Bypasses (http://forum.peundemerg.ro/index.php?topic=446.msg127878#msg127878)

September 2016: Motorways: plans and projects (http://forum.peundemerg.ro/index.php?topic=446.msg130855#msg130855)  *  A1 Bucharest - Nădlac (http://forum.peundemerg.ro/index.php?topic=446.msg130856#msg130856)  *  A3 Bucharest - Borș (http://forum.peundemerg.ro/index.php?topic=446.msg130857#msg130857)  *  A7 Ploiești - Bacău - Siret (http://forum.peundemerg.ro/index.php?topic=446.msg130858#msg130858)  *  A10 Sebeș - Turda (http://forum.peundemerg.ro/index.php?topic=446.msg130859#msg130859)  *  National roads (http://forum.peundemerg.ro/index.php?topic=446.msg130860#msg130860)  *  Bypasses (http://forum.peundemerg.ro/index.php?topic=446.msg130861#msg130861)

October 2016: Motorways: plans and projects (http://forum.peundemerg.ro/index.php?topic=446.msg136111#msg136111)  *  A1 Bucharest - Nădlac (http://forum.peundemerg.ro/index.php?topic=446.msg136112#msg136112)  *  A3 Bucharest - Borș (http://forum.peundemerg.ro/index.php?topic=446.msg136113#msg136113)  *  A7 Ploiești - Bacău - Siret (http://forum.peundemerg.ro/index.php?topic=446.msg136114#msg136114)  *  A10 Sebeș - Turda (http://forum.peundemerg.ro/index.php?topic=446.msg136115#msg136115)  *  National roads (http://forum.peundemerg.ro/index.php?topic=446.msg136116#msg136116)  *  Bypasses (http://forum.peundemerg.ro/index.php?topic=446.msg136117#msg136117)

November 2016: Motorways: plans and projects (http://forum.peundemerg.ro/index.php?topic=446.msg143095#msg143095)  *  A1 Bucharest - Nădlac (http://forum.peundemerg.ro/index.php?topic=446.msg143096#msg143096)  *  A3 Bucharest - Borș (http://forum.peundemerg.ro/index.php?topic=446.msg143097#msg143097)  *  A7 Ploiești - Bacău - Siret (http://forum.peundemerg.ro/index.php?topic=446.msg143098#msg143098)  *  A10 Sebeș - Turda (http://forum.peundemerg.ro/index.php?topic=446.msg143099#msg143099)  *  National roads (http://forum.peundemerg.ro/index.php?topic=446.msg143100#msg143100)  *  Bypasses (http://forum.peundemerg.ro/index.php?topic=446.msg143101#msg143101)

December 2016: Motorways: plans and projects (http://forum.peundemerg.ro/index.php?topic=446.msg144852#msg144852)  *  A1 Bucharest - Nădlac (http://forum.peundemerg.ro/index.php?topic=446.msg144853#msg144853)  *  A3 Bucharest - Borș (http://forum.peundemerg.ro/index.php?topic=446.msg144854#msg144854)  *  A7 Ploiești - Bacău - Siret (http://forum.peundemerg.ro/index.php?topic=446.msg144855#msg144855)  *  A10 Sebeș - Turda (http://forum.peundemerg.ro/index.php?topic=446.msg144856#msg144856)  *  National roads (http://forum.peundemerg.ro/index.php?topic=446.msg144857#msg144857)  *  Bypasses (http://forum.peundemerg.ro/index.php?topic=446.msg144858#msg144858)

January 2017: Motorways: plans and projects  *  A1 Bucharest - Nădlac (http://forum.peundemerg.ro/index.php?topic=446.msg146880#msg146880)  *  A3 Bucharest - Borș  *  A7 Ploiești - Bacău - Siret (http://forum.peundemerg.ro/index.php?topic=446.msg146881#msg146881)  *  A10 Sebeș - Turda (http://forum.peundemerg.ro/index.php?topic=446.msg146882#msg146882)  *  National roads  *  Bypasses (http://forum.peundemerg.ro/index.php?topic=446.msg146883#msg146883)

February 2017: Motorways: plans and projects (http://forum.peundemerg.ro/index.php?topic=446.msg153131#msg153131)  *  A1 Bucharest - Nădlac (http://forum.peundemerg.ro/index.php?topic=446.msg153132#msg153132)  *  A3 Bucharest - Borș (http://forum.peundemerg.ro/index.php?topic=446.msg153133#msg153133)  *  A7 Ploiești - Bacău - Siret (http://forum.peundemerg.ro/index.php?topic=446.msg153134#msg153134)  *  A10 Sebeș - Turda (http://forum.peundemerg.ro/index.php?topic=446.msg153135#msg153135)  *  National roads (http://forum.peundemerg.ro/index.php?topic=446.msg153136#msg153136)

March 2017: Motorways: plans and projects (http://forum.peundemerg.ro/index.php?topic=446.msg153140#msg153140)  *  A1 Bucharest - Nădlac (http://forum.peundemerg.ro/index.php?topic=446.msg153141#msg153141)  *  A3 Bucharest - Borș (http://forum.peundemerg.ro/index.php?topic=446.msg153142#msg153142)  *  A7 Ploiești - Bacău - Siret (http://forum.peundemerg.ro/index.php?topic=446.msg153143#msg153143)  *  A10 Sebeș - Turda (http://forum.peundemerg.ro/index.php?topic=446.msg153144#msg153144)  *  National roads (http://forum.peundemerg.ro/index.php?topic=446.msg153145#msg153145)  *  Bypasses (http://forum.peundemerg.ro/index.php?topic=446.msg153146#msg153146)

April 2017: Motorways: plans and projects (http://forum.peundemerg.ro/index.php?topic=446.msg155541#msg155541)  *  A1 Bucharest - Nădlac (http://forum.peundemerg.ro/index.php?topic=446.msg155542#msg155542)  *  A3 Bucharest - Borș (http://forum.peundemerg.ro/index.php?topic=446.msg155543#msg155543)  *  A7 Ploiești - Bacău - Siret (http://forum.peundemerg.ro/index.php?topic=446.msg155544#msg155544)  *  A10 Sebeș - Turda (http://forum.peundemerg.ro/index.php?topic=446.msg155545#msg155545)  *  National roads (http://forum.peundemerg.ro/index.php?topic=446.msg155546#msg155546)  *  Bypasses (http://forum.peundemerg.ro/index.php?topic=446.msg155547#msg155547)


List of abbreviations: (asp) = and subsequent posts (warns that the direct link is only to the first post in a series; mostly used for relevant posts not necessarily in a consecutive arrangement, i.e. series likely interrupted by other posts); An = motorway n; DN n = national road n; DXn = Expressway n (basically a motorway without hard shoulders and with reduced lane width; none exists yet); FS = feasibility study; GTMP = General Transport Masterplan; LIOP = Large Infrastructure Operational Programme 2014 – 2020; NCARI = National Company for the Administration of Road Infrastructure; PIA = Pro Infrastructure Association, the NGO associated with this forum; RNCMNR = Romanian National Company for Motorways and National Roads.

Note: In Fall 2016 the RNCMNR was reorganised into NCARI (dealing with administration and maintenance of national roads) and NCRI (National Company for Road Investments, dealing with project preparation and implementation for constructing national roads). Since the latter is not yet functional, NCARI is de facto fulfilling its roles at the moment.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on June 18, 2016, 03:01:25 AM
May 2016 * Motorways: plans and projects

05/04 (http://forum.peundemerg.ro/index.php?topic=9.msg115330#msg115330)  It appears that there is some slow progress for the Sibiu - Făgăraș motorway feasibility study (western part of A13) (contract signed in April 2015).
05/05 (http://forum.peundemerg.ro/index.php?topic=9.msg115427#msg115427)  Discussions around some press articles showing no success with attracting financing from the European Commission's Investment Plan for Europe (the "Juncker Plan") (article 1 (http://cursdeguvernare.ro/ce-a-refuzat-romania-sa-inteleaga-din-planul-junker-astfel-incat-i-au-picat-toate-proiectele-propuse.html), article 2 (http://www.hotnews.ro/stiri-opinii-20964183-fondul-european-pentru-investitii-strategice-sansa-care-romania-nu-poate-permite-piarda.htm)), as well as problems and delays regarding the Large Infrastructure Operational Programme (LIOP) 2014 - 2020 (article 3 (http://www.digi24.ro/Stiri/Digi24/Economie/Stiri/Programul+Operational+Infrastructura+Pierdem+bani+inainte+de+a+i)).
05/30 (http://forum.peundemerg.ro/index.php?topic=9.msg118274#msg118274)  The Ministry of European Funds has launched a financing call (http://www.fonduri-ue.ro/presa/comunicate/1903-comunicat-30-05-2016) for the LIOP 2014 - 2020 for road, rail and subway infrastructure projects (total allocation is 5.8 billion Euro, of which 3.27 billion Euro for roads - eligible applicant being the RNCMNR only), with applications accepted in the period June 1, 2016 - December 31, 2018.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on June 18, 2016, 03:04:28 AM
May 2016 * A1 Bucharest - Nădlac

05/01 Clarifications regarding wildlife crossings (http://forum.peundemerg.ro/index.php?topic=2.msg115059#msg115059) on Lugoj - Deva motorway section 3.
05/02 Construction pics (http://forum.peundemerg.ro/index.php?topic=2.msg115119#msg115119) and video from Ohaba (http://forum.peundemerg.ro/index.php?topic=2.msg115124#msg115124) (Lugoj - Deva motorway section 3).
05/08 Inventory of problems (http://forum.peundemerg.ro/index.php?topic=2.msg115828#msg115828) to be solved regarding the Lugoj - Deva motorway such that this project can better progress.
05/08 Construction pics (http://forum.peundemerg.ro/index.php?topic=2.msg115838#msg115838) from around the Grind interchange (Lugoj - Deva motorway section 3).
05/10 Data from the official RNCMNR May report (http://forum.peundemerg.ro/index.php?topic=2.msg116006#msg116006) regarding the status of the Lugoj - Deva motorway.
05/10 Comments on major technical risks (http://forum.peundemerg.ro/index.php?topic=2.msg116015#msg116015) regarding Lugoj - Deva motorway section 4.
05/13 Pictures (http://forum.peundemerg.ro/index.php?topic=2.msg116369#msg116369) from the Orăștie - Sibiu motorway section 3. No progress regarding reopening of the motorway; terrain slides are actually getting worse.
05/14 RNCMNR general director visits the Lugoj - Deva motorway (http://forum.peundemerg.ro/index.php?topic=2.msg116464#msg116464) construction site. "Ultimatum" given to the contractor on section 2 to ramp up works.
05/15 Construction pics (http://forum.peundemerg.ro/index.php?topic=2.msg116508#msg116508) taken from a train (Lugoj - Deva motorway section 4). Further post shows the Orăștie - Sibiu motorway section 3 - currently closed to traffic.
05/15 Construction pics (http://forum.peundemerg.ro/index.php?topic=2.msg116536#msg116536) mostly from around Grind interchange (Lugoj - Deva motorway section 3).
05/16 Ample set of construction pics (starts here (http://forum.peundemerg.ro/index.php?topic=2.msg116644#msg116644)) from Lugoj - Deva motorway sections 2, 3 and 4.
05/18 The very first set of pics showing on-site proof of ongoing geotechnical studies (http://forum.peundemerg.ro/index.php?topic=2.msg116795#msg116795) for the Sibiu - Boița section part of the Sibiu - Pitești motorway.
05/18 Realistic proposal for a calendar (http://forum.peundemerg.ro/index.php?topic=2.msg116879#msg116879) for the construction of the end sections ("the easy ones", Sibiu - Boița and Curtea de Argeș - Pitești) of the Sibiu - Pitești motorway.
05/20 Construction pics (http://forum.peundemerg.ro/index.php?topic=2.msg117189#msg117189) from Șoimuș (Lugoj - Deva motorway section 4).
05/20 Ample set of pics (http://forum.peundemerg.ro/index.php?topic=2.msg117202#msg117202) showing the current status of the Orăștie - Sibiu motorway section 3 (closed to traffic) - focused on the many technical / in situ problems.
05/22 Construction pics (http://forum.peundemerg.ro/index.php?topic=2.msg117340#msg117340) from Lugoj - Deva motorway section 4.
05/24 Construction videos (http://forum.peundemerg.ro/index.php?topic=2.msg117605#msg117605) from Lugoj - Deva motorway section 3.
05/25 RNCMNR appears to be making some progress (video (http://forum.peundemerg.ro/index.php?topic=2.msg117754#msg117754)) regarding the "reconstruction" of troubled subsections from the Orăștie - Sibiu motorway section 3 (closed to traffic), followed by press release describing ongoing government efforts in this direction.
05/28 Construction pics (http://forum.peundemerg.ro/index.php?topic=2.msg118059#msg118059) from Lugoj - Deva motorway section 2, as well as section 3 (http://forum.peundemerg.ro/index.php?topic=2.msg118122#msg118122).
05/30 Construction video (http://forum.peundemerg.ro/index.php?topic=2.msg118292#msg118292) from Lugoj - Deva motorway section 2.
05/30 Comments regarding the status of the construction works (http://forum.peundemerg.ro/index.php?topic=2.msg118319#msg118319) on Lugoj - Deva motorway section 2.
05/31 Ample set of construction pics (starts here (http://forum.peundemerg.ro/index.php?topic=2.msg118460#msg118460)) from Lugoj - Deva motorway sections 2, 3 and 4.
05/31 Ministry of Transport states (http://forum.peundemerg.ro/index.php?topic=2.msg118504#msg118504) that an additional number of 1377 plots of land still need to be expropriated as pertaining to the Orăștie - Sibiu motorway (that was opened to traffic some years ago).
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on June 18, 2016, 03:06:09 AM
May 2016 * A3 Bucharest - Borș

04/30 (http://forum.peundemerg.ro/index.php?topic=6.msg115003#msg115003) Feasibility study ready for 4 out of 5 sectors for the Mihăiești - Suplacu de Barcău section, environmental permit to be out soon; it would be possible to tender these sectors for ERDF financing. Construction contract signature for Nădășel - Mihăiești sector expected to take place soon.
05/01 (http://forum.peundemerg.ro/index.php?topic=6.msg115060#msg115060) The constructor of the Suplacu de Barcău - Borș section drafted and signed new rental agreements with some owners of land used for motorway construction - and rental compensations started to be paid.
05/04 Notice to commence the design&build contract (http://forum.peundemerg.ro/index.php?topic=6.msg115346#msg115346) was submitted to the contractors for the following three sectors of the Târgu Mureș - Câmpia Turzii section:
Construction will be cofinanced by the EU through the Cohesion Fund. The design period is 4 months, and the construction period 12 months. As such, these contracts should be completed by September 4, 2017.
05/10 Data from the official RNCMNR May report (http://forum.peundemerg.ro/index.php?topic=6.msg116000#msg116000) regarding the status of the various sections of the A3 motorway under preparation or construction. Construction progress of the Gilău - Nădășel section (the only one currently under construction) advanced during the last month from 68.56% to 70.69%.
05/18 Preliminary works (http://forum.peundemerg.ro/index.php?topic=6.msg116915#msg116915) taking place on the three sectors mentioned above (05/04): archaelogical clearance, demining, boring for geotechnical investigations, construction site marking, errection of the construction camps.
05/24 Construction videos (http://forum.peundemerg.ro/index.php?topic=6.msg117509#msg117509) (scroll for the second video) from the Gilău - Nădășel motorway.
05/26 Contract signature: the design&build contract for the 16.8 km motorway sector Nădășel - Mihăiești (sector km 8+700 – km 25+500 of the 3A section) was signed today (http://forum.peundemerg.ro/index.php?topic=6.msg117841#msg117841) between the RNCMNR and the contractor Impresa Construzioni Giuseppe Maltauro SpA - S.C. Viaponte ROM S.R.L.. Total value is 446,127,400.01 RON (VAT excluded). Financing is to be ensured from the national budget, with a contract duration of 18 months (6 months design + 12 months construction) - computed from the date of the order of commencement (date not specified).
05/29 Ample set of construction pics (http://forum.peundemerg.ro/index.php?topic=6.msg118107#msg118107) from the Gilău - Nădășel motorway.
05/31 Construction video (http://forum.peundemerg.ro/index.php?topic=6.msg118423#msg118423) (covering the entire alignment) from the Gilău - Nădășel motorway.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on June 18, 2016, 03:07:08 AM
May 2016 * A7 Ploiești - Bacău - Siret

05/04 (http://forum.peundemerg.ro/index.php?topic=58.msg115338#msg115338)  For the entire A7/DX7 [except the Bacău bypass, construction to commence soon] the RNCMNR has not even yet launched the tenders for the feasibility studies. A realistic estimate appears to be 2018 for finalising preparatory studies and 2020 for commencement of works.
05/10 (http://forum.peundemerg.ro/index.php?topic=58.msg116089#msg116089)  Data from the official RNCMNR May report (http://cnadnr.ro/img/tabel/STADIULPROIECTELORINDERULARE.pdf) regarding the status of the Bacău bypass: construction site handover on May 6, construction to start on May 25.
05/18 (http://forum.peundemerg.ro/index.php?topic=58.msg116925#msg116925)  According to press article (http://zdbc.ro/cnadr-a-finalizat-caietele-de-sarcini-pentru-autostrada-bacau-ploiesti-licitatia-ar-putea-fi-lansata-in-luna-iunie/), RNCMNR has finalised tender documents for the Ploiești - Bacău motorway/expressway studies (feasibility study + design + construction permit, i.e. apparently to be prepared for a Red FIDIC contract-type), and they have been submitted to JASPERS. Tender could start in June.
05/24 (http://forum.peundemerg.ro/index.php?topic=58.msg117588#msg117588)  Works commence for the Bacău half-motorway bypass. Pictures here (http://forum.peundemerg.ro/index.php?topic=58.msg117593#msg117593), showing clearing and grubbing activities.
05/30 (http://forum.peundemerg.ro/index.php?topic=58.msg118176#msg118176)  Works for the second carriageway to be performed apparently up to the base course, with only asphalt (and corresponding finishing works - e.g signage) to be remaining for a future contract of converting the bypass into a full motorway (for the section between DN 2 south and DN 2 north)...
05/30 (http://forum.peundemerg.ro/index.php?topic=58.msg118203#msg118203)  ...however some structures appear to be constructed only for the first carriageway.
05/30 (http://forum.peundemerg.ro/index.php?topic=58.msg118269#msg118269)  Some press articles (article 1 (http://zdbc.ro/video-foto-au-inceput-lucrarile-la-centura-bacaului-dragos-benea-cea-mai-importanta-investitie-din-ultimii-25-de-ani/), article 2 (http://www.agerpres.ro/economie/2016/05/30/lucrarile-la-centura-ocolitoare-a-muncipiului-bacau-inaugurate-in-prezenta-ministrului-transporturilor-16-33-06), article 3 (http://www.capital.ro/lucrarile-la-centura-ocolitoare-a-muncipiului-bacau-inaugurate-in-prezenta-ministrului-transporturilor.html)) showing start of construction works on the Bacău bypass, as well as data about the project.
05/31  Link to the Bacău bypass project map (http://forum.peundemerg.ro/storage/images/autostrada_centura_bacau_bypass.jpg).
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on June 18, 2016, 03:08:01 AM
May 2016 * A10 Sebeș - Turda

05/01  Construction pics (http://forum.peundemerg.ro/index.php?topic=165.msg115078#msg115078) from section 4.
05/06  Construction pics (http://forum.peundemerg.ro/index.php?topic=165.msg115661#msg115661) from section 2.
05/06  Construction pics (http://forum.peundemerg.ro/index.php?topic=165.msg115681#msg115681) from section 4.
05/10 (http://forum.peundemerg.ro/index.php?topic=165.msg115999#msg115999)  Data from the official RNCMNR May report (http://cnadnr.ro/img/tabel/STADIULPROIECTELORINDERULARE.pdf) regarding the status of the Sebeș - Turda motorway. Construction progress from April to May: Section 1: 12.27% to 12.55%; Section 2: 8.30% to 8.58%; Section 3: remains at 48.68%; Section 4: 46.13% to 47.00%. Major problem appears to be the absence of construction permits for many subsections.
05/13  Construction pics (http://forum.peundemerg.ro/index.php?topic=165.msg115681#msg115681) from section 2, works acceleration noticed; unfortunately no works on section 3 (pics of construction site) (http://forum.peundemerg.ro/index.php?topic=165.msg116383#msg116383).
05/15  Construction site pics (http://forum.peundemerg.ro/index.php?topic=165.msg116534#msg116534) from section 2.
05/19 (http://forum.peundemerg.ro/index.php?topic=165.msg116984#msg116984)  Additional land acquisition decisions, as needed for section 3.
05/19  Construction pics (http://forum.peundemerg.ro/index.php?topic=165.msg117080#msg117080) from section 2, again showing acceleration of works.
05/21  More construction pics (http://forum.peundemerg.ro/index.php?topic=165.msg117273#msg117273) from section 2.
05/24  Construction pics (http://forum.peundemerg.ro/index.php?topic=165.msg117472#msg117472) from the A3-A10 in interchange (at Turda), part of section 4.
05/25  Poppy flowers growing on motorway construction alignment (http://forum.peundemerg.ro/index.php?topic=165.msg117689#msg117689) (section 1) - picture became widely distributed by the media.
05/27  Construction pics (http://forum.peundemerg.ro/index.php?topic=165.msg117962#msg117962) from section 4, including the A3-A10 interchange.
05/28  Construction pics (http://forum.peundemerg.ro/index.php?topic=165.msg118016#msg118016) from sections 4 and 3 (includes subsequent posts).
05/31  Construction pics (http://forum.peundemerg.ro/index.php?topic=165.msg118392#msg118392) showing bridge beam placement for the first overpass of A10 over A3 at the Turda interchange between the two motorways (also subsequent posts).
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on June 18, 2016, 03:09:04 AM
May 2016 * National roads

04/30  Alignment map (http://forum.peundemerg.ro/index.php?topic=12.msg115025#msg115025) for the future A1 - DN 69 expressway connector north of Timișoara (design under completion).
05/03  Site pics (http://forum.peundemerg.ro/index.php?topic=12.msg115227#msg115227) from the infamous project of modernising DN 76 between Deva and Oradea, started over 10 years ago. No works on this specific section, road in very bad shape...
05/04  ...followed by a video (http://forum.peundemerg.ro/index.php?topic=12.msg115271#msg115271) from a different section of the same road (DN 76).
05/05 (http://forum.peundemerg.ro/index.php?topic=12.msg115424#msg115424)  The EC approves retroactive financing for one of the Roads 6 projects: DN 15/15A Târgu Mureș - Reghin - Sărățel. EU contribution is over 31 million euro.
05/06  Detailed article (http://forum.peundemerg.ro/index.php?topic=12.msg115667#msg115667) about the major failure regarding the DN 76 modernisation.
05/11  Site pics (http://forum.peundemerg.ro/index.php?topic=12.msg116111#msg116111) from DN 18 Moisei - Iacobeni: the only failed project of the 16 road rehabilitation projects in the Roads 6 programme.
05/14 (http://forum.peundemerg.ro/index.php?topic=12.msg116467#msg116467)  Official statement (http://cnadnr.ro/docs/comunicate/Comunicat%20CNADNR%20SA%2013%2005%202016%20ref%20%20situatie%20lucrari%20DN%2076.pdf) from the RNCMNR regarding the status of works for the modernisation of DN 76 Deva - Oradea...
05/19 (http://forum.peundemerg.ro/index.php?topic=12.msg117045#msg117045)  ...followed by a site visit of the General Director of the RNCMNR on this road; progress of works appears to be as follows:
05/28  Site/construction pics (http://forum.peundemerg.ro/index.php?topic=12.msg118065#msg118065) regarding the modernisation of the DN 5 Bucharest - Adunații Copăcenii sector (delayed for over one decade, but important E-road as well as part of TEN-T Core) (continued in multiple subsequent posts).
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on June 18, 2016, 03:09:52 AM
May 2016 * Bypasses

05/14 (http://forum.peundemerg.ro/index.php?topic=7.msg116456#msg116456) Data from the official RNCMNR May report (http://cnadnr.ro/img/tabel/STADIULPROIECTELORINDERULARE.pdf) regarding the status of various bypass construction:
05/27  Construction pics (http://forum.peundemerg.ro/index.php?topic=7.msg117967#msg117967) from grade separation works on the Oradea bypass.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on June 18, 2016, 03:28:13 AM
[Temp]
Obiectivul este realizarea, în engleză, a unei sinteze (pentru fiecare subiect indicat în prima postare) în care să fie trecute principalele progrese / update-uri / idei discutate + poze/video de la șantiere (sau locații, aliniamente), cu link-uri la postările în .ro.
Scopul este de a ajuta pe cei interesați care nu vorbesc română să găsească informații. Dar, în plus, de a avea o sinteză ușor accesibilă (pentru cei care lipsesc o vreme de pe forum... + pentru a putea urmări lucrurile de-a lungul lunilor sau anilor... etc.)
Propun o perioadă de comentarii privind posibile îmbunătățiri.
Apoi Ionuț poate decide ce face cu thread-ul (pinned? restricted posting? feeding the always hungry thrash can? :D)
Cred că acest thread nu ar trebui să se transforme într-unul de întrebări în limba engleză (no offense, AUT_XY). Poate pentru asta ar trebui alt thread (și, generalmente vorbind, poate un thread general de întrebări pentru useri ce postează în română).
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: TibiV on June 18, 2016, 11:21:51 AM
[Temp]

The trash can is not so hungry !...
:gj:
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: Ionut on June 18, 2016, 05:04:46 PM
Facem topicul "sticky". Good job! :cheers:
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: icristian on June 22, 2016, 03:30:45 PM
+1 North imi place ce ai facut, poti urmari foarte usor progresul sau atunci cand vrei sa cauti un eveniment mai deosebit.
O remarca RNCMNR e foarte confuz, poate ar trebui pastrat termenul de CNADNR, iar la legenda (abbreviation list) poate fi explicat in engleza.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on July 01, 2016, 02:05:57 AM
June 2016 * Motorways: plans and projects

06/01  The RNCMNR presents, in a press release (http://www.cnadnr.ro/docs/comunicate/Comunicat%20CNADNR%20SA%2001.06.2016%20ref.pdf), the list of projects it intends to promote for the financing call launched by the Ministry of EU Funds on 05/30 (http://forum.peundemerg.ro/index.php?topic=446.msg120530#msg120530). Regarding new high speed roads (motorways and expressways), this includes the Sibiu - Pitești motorway, the Ploiești - Bacău expressway and a short expressway link between the Bucharest airport and A3 motorway.
06/03 (http://forum.peundemerg.ro/index.php?topic=9.msg118954#msg118954)  Amidst a discussion regarding the lack of prepared high speed road projects for 2014 - 2020 EU financing and the risks related to only preparing a few large projects, a portfolio of potential project ideas (motorways and expressways) is proposed, that could be at least in part implemented within this planning period (including 2023).
06/04 (http://forum.peundemerg.ro/index.php?topic=9.msg119055#msg119055)  The years 2018 - 2020 will be the most difficult to account for in terms of EU funds absorption. The only way to avoid this is to immediately launch the limited set of already prepared motorway projects, i.e. sections of A3.
06/17 (http://forum.peundemerg.ro/index.php?topic=9.msg120489#msg120489)  A post with a link to the list of projects to be financed in Romania via the "Juncker Plan" - second call. No motorway projects are included (however, these are rarely included even for other countries).
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on July 01, 2016, 02:06:24 AM
June 2016 * A1 Bucharest - Nădlac

06/02 (http://forum.peundemerg.ro/index.php?topic=2.msg118830#msg118830)  Discussion continuing over several posts about the significantly delayed preparation of the Sibiu - Pitești motorway section, with arguments for and against a priority treatment for the end sections (1 and 5) of the motorway in regards to obtaining the Environmental Permit. Features a blunt (but realistic) statement of Carsten Rasmussen, Deputy Head of Unit DG Regio regarding the disastrous stage of prepartion for this project, addressed towards the RNCMNR representative at a Transport Subcommittee meeting connected to the LIOP Monitoring Committee.
06/09 (http://forum.peundemerg.ro/index.php?topic=2.msg119592#msg119592)  Dashcam video from the Pitești - Bucharest A1 shows significant maintenance issues on this motorway section, discussion focused on the administrator's (RNCMNR) carelessness.
06/10  Ample set of Construction pics (http://forum.peundemerg.ro/index.php?topic=2.msg119885#msg119885) from Lugoj - Deva motorway section 4.
06/20 (http://forum.peundemerg.ro/index.php?topic=2.msg120643#msg120643)  Video of the western part (Traian Vuia - Colonia Mică) part of the Lugoj - Deva motorway section 2. Can be compared with video covering the same location from 04/17 (referenced in the post).
06/20 (http://forum.peundemerg.ro/index.php?topic=2.msg120668#msg120668)  According to an interview with the specialty subcontractor, boring for geotechnical investigations [part of the feasibility study] for the Sibiu - Pitești motorway could be completed before the end of this year.
06/21  Data from the official RNCMNR June report (http://cnadnr.ro/img/tabel/STADIULPROIECTELORINDERULARE.pdf) regarding the status of Lugoj - Deva sections 2, 3 and 4 (currently the only sections under construction part of A1): construction status is at 40.95% (Section 2), 51.48% (Section 3) and 47.12% (Section 4).
06/21 (http://forum.peundemerg.ro/index.php?topic=2.msg120753#msg120753)  Ample set of pics from Orăștie - Sibiu motorway section 3 (currently closed to traffic) showing many major construction faults (especially in regards to drainage), as well as virtually no progress regarding the ~200-m demolished section between September 2015 and June 2016. No reconstruction activities appear to be taking place on the site.
06/22 (http://forum.peundemerg.ro/index.php?topic=2.msg120879#msg120879)  Construction pics from Lugoj - Deva motorway sections 2 and 3.
06/27 (http://forum.peundemerg.ro/index.php?topic=2.msg121230#msg121230)  Disappointment regarding the lack of progress in solving the environmental issues for Lugoj - Deva section 4. The probability of finalizing this section before 2018 is minuscule.
06/29 (http://forum.peundemerg.ro/index.php?topic=2.msg121498#msg121498)  Video showing the construction progress on Lugoj - Deva sections 3 and 4 and a brief discussion of a realistic timeline for opening to traffic the entire Dumbrava - Deva motorway, showing that each of the three sections has major issues preventing full operation before 2018: the sector with tunnels on section 2, construction of the Holdea interchange on section 3, obtaining the environmental permit for 11 km (of total 22) on section 4 (it is noted that 3 years after the contract signing there is no environmental permit - and hence construction permit - for these 11 km).
06/29 (http://forum.peundemerg.ro/index.php?topic=2.msg121512#msg121512)  Video showing the construction progress on Lugoj - Deva section 2; there is a significant chance that the sector Dumbrava - Margina will be open to traffic end of 2016.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on July 01, 2016, 02:06:44 AM
June 2016 * A3 Bucharest - Borș

06/01 Notice to commence the design&build contract (http://cnadnr.ro/docs/comunicate/Comunicat%20CNADNR%20SA%2001%2006%202016%20ref%20%20Ordin%20de%20Incepere%20Lucrari%20autostrada%20Tg%20%20Mures-%20Ogra%20Lot%202%20Ungheni%20-%20Ogra.pdf) was submitted to the contractor for the following section of the Târgu Mureș - Câmpia Turzii motorway:
The construction permit was also issued (http://forum.peundemerg.ro/index.php?topic=6.msg118634#msg118634) this same day[/url].
Construction will be cofinanced by the EU through the Cohesion Fund. The construction period is 12 months. As such, this contract should be completed by May 31, 2017.
06/08 (http://forum.peundemerg.ro/index.php?topic=6.msg119578#msg119578)  Well-argued point of view regarding the current unrealistic timelines for D&B contracts (Yellow FIDIC type). Proposal is that there should be three stages: 4-6 months design; 10-12 months approvals and land acquisition; 10-12 months construction.
06/09 (http://forum.peundemerg.ro/index.php?topic=6.msg119611#msg119611)  No progress for the construction of the southernmost 3 km of A3 (inside Voluntari and Bucharest), and - due to permitting issues - it appears that construction will not start before 2017.
06/13  Impressive video (http://forum.peundemerg.ro/index.php?topic=6.msg120127#msg120127) showing extreme construction mobilization for the km 9 cut section of the Gilău - Nădășel motorway.
09/16 (http://forum.peundemerg.ro/index.php?topic=6.msg120308#msg120308)  There appears to be good news regarding the progress on the Nădășel - Mihăiești (topographical and geotechnical investigations as well as demining) and Suplacu de Barcău - Borș (design and letter of bank guarantee submitted) A3 motorway sections.
06/17 (http://forum.peundemerg.ro/index.php?topic=6.msg120492#msg120492)  Pics documenting preparatory works on the Suplacu de Barcău - Borș section.
06/19 (http://forum.peundemerg.ro/index.php?topic=6.msg120603#msg120603)  Ample set of pics regarding the current status of the abandoned construction works that have been conducted between 2004 and 2011 on the Suplacu de Barcău - Borș section by the Bechtel / Enka joint venture.
06/21 (http://forum.peundemerg.ro/index.php?topic=6.msg120748#msg120748)  Data from the official RNCMNR May report regarding the status of the various sections of the A3 motorway under preparation or construction. Construction progress for the Gilău - Nădășel section (the only one currently under construction) advanced during the last month from 70.69% to 74.34%.
06/24  Construction video (http://forum.peundemerg.ro/index.php?topic=6.msg121064#msg121064) from the Gilău - Nădășel motorway.
06/27 (http://forum.peundemerg.ro/index.php?topic=6.msg121240#msg121240)  (and subsequent post) First pictures of construction works from Iernut - Chețani motorway section.
06/28  End-June construction pics (http://forum.peundemerg.ro/index.php?topic=6.msg121357#msg121357) from the Gilău - Nădășel motorway, varying from excavation to asphalt/finishing works.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on July 02, 2016, 02:09:45 AM
June 2016 * A7 Ploiești - Bacău - Siret

06/02 (http://forum.peundemerg.ro/index.php?topic=58.msg118841#msg118841)  Today, during the Transport Subcommittee meeting (part of the LIOP Monitoring Committee), the API representative requested that the tender book for the feasibility study for the A7 motorway (section Ploiești - Bacău) should include the request to conduct a CBA to analyze the opportunity of constructing this section as a motorway instead of an expressway (as currently specified in the General Transport Masterplan).
06/07 (http://forum.peundemerg.ro/index.php?topic=58.msg119367#msg119367)  Link to pictures showing progress in the errection of the construction camp for the Bacău bypass.
06/11 (http://forum.peundemerg.ro/index.php?topic=58.msg119961#msg119961)  It appears that the contractor's Facebook page (https://www.facebook.com/EkoConstructionTradeCoInc/posts/1021725957947392) will be a good source to track the progress of the Bacău bypass construction project.
06/20 (http://forum.peundemerg.ro/index.php?topic=58.msg120652#msg120652)  According to an article in the local press (http://www.desteptarea.ro/centura-bacaului-faza-arheologica/), a contractor's representative estimates that the demining and archaelogical clearance activities will take approximately two months, with the actual construction activities to start immediately after that. The article comments also on problems related to land acquisition (specifically regarding fair compensation) connected to this project.
06/28 (http://forum.peundemerg.ro/index.php?topic=58.msg121327#msg121327)  Brief discussion about the fact that the plan to construct only one carriageway of the Bacău motorway bypass is probably out-of-date in terms of projected traffic volumes.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on July 02, 2016, 02:10:03 AM
June 2016 * A10 Sebeș - Turda

06/01  Construction pics (http://forum.peundemerg.ro/index.php?topic=165.msg118680#msg118680) from section 2.
06/01  Construction pics (http://forum.peundemerg.ro/index.php?topic=165.msg118695#msg118695) from sections 3 and 4.
06/08 (http://forum.peundemerg.ro/index.php?topic=165.msg119462#msg119462)  Disappointment rises regarding the inability of the authorities to provide construction permits for the entire motorway (ironically, according to the contracts, sections 3 and 4 should have been completed by May 31, 2016!) and the apparent lack of interest to expedite the construction progress.
06/08  Construction pics (http://forum.peundemerg.ro/index.php?topic=165.msg119562#msg119562) from section 2.
06/09  Many construction pictures (http://forum.peundemerg.ro/index.php?topic=165.msg119693#msg119693) from section 4, emphasizing segments where works cannot progress due to the lack of a construction permit, as well as transmission towers on the motorway alignment that still need to be relocated.
06/21 (http://forum.peundemerg.ro/index.php?topic=165.msg120751#msg120751)  Data from the official RNCMNR June report regarding the status of the Sebeș - Turda motorway. Construction progress from May to June: Section 1: remains at 12.55%; Section 2: 8.58% to 9.28%; Section 3: remains at 48.68%; Section 4: 47.00% to 47.50%.
06/28 (http://forum.peundemerg.ro/index.php?topic=165.msg121387#msg121387)  Construction permits finally in force for Section 1 (14 of 17 km) and Section 3 (entire section). Section 2 already has CP for its entire length, CP for remaining parts of Section 4 to be issued "within days".
06/28 (http://forum.peundemerg.ro/index.php?topic=165.msg121441#msg121441)  Video (https://www.youtube.com/watch?v=W2tdL1B-mPI) showing the alignment / construction progress for the entire motorway.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on July 02, 2016, 02:10:23 AM
June 2016 * National roads

06/08 (http://forum.peundemerg.ro/index.php?topic=12.msg119429#msg119429)  Technical details from the feasibility study of the future A1 - DN 69 expressway connector north of Timișoara (link to alignment (http://forum.peundemerg.ro/index.php?topic=7.msg115050#msg115050)). It will be a 2x2 road with a 1.5 m median (probably equipped with Jersey barriers) and 2.5 m shoulders (probably soft), with a total platform width of 20.5 m.
06/08 (http://forum.peundemerg.ro/index.php?topic=12.msg119506#msg119506)  The EC approves retroactive financing for one more Roads 6 project: contract 6R8 for the modernisation of DN 1C/19 Baia Mare - Satu Mare and Livada - Halmeu (RO/UA border). EU contribution is around 31 million euro.
06/08 (http://forum.peundemerg.ro/index.php?topic=12.msg119565#msg119565)  Three simultaneous protests on DN 76 (the project to modernize DN 76 Deva - Oradea, started over 10 years ago). The road (an E-road, E79) was blocked for some time.
06/09 (http://forum.peundemerg.ro/index.php?topic=12.msg119656#msg119656)  According to a press release (http://cnadnr.ro/docs/comunicate/1_Comunicat%20CNADNR%20SA%2009%2006%202016%20reabilitarea%20DN%2018,%20Moisei%20-%20Iacobeni%20.pdf) from the RNCMNR, the design&build contract for the rehabilitation of the Cârlibaba – Iacobeni (km 199+400 - km 220+088) segment of the DN 18 Moisei - Iacobeni section (formerly contract 6R13) was signed today. The contractor is SC Autotehnorom SRL - SC OPR Asfalt SRL - SC Procad SRL, and the contract value is 59,840,261.94 RON (VAT excluded). The D&B contract period is 24 months (of which the first 4 months reserved for design).
06/13 (http://forum.peundemerg.ro/index.php?topic=12.msg120061#msg120061)  Construction pics from the modernisation of DN 76 section 5 (contractor is Azvi).
06/15 (http://forum.peundemerg.ro/index.php?topic=12.msg120243#msg120243)  Selina has taken over the contract (former contractor: Construct Mod) regarding the modernisation of DN 76, section Vârfurile – Ştei (km 69+350 – km 102+660).
06/15 (http://forum.peundemerg.ro/index.php?topic=12.msg120245#msg120245)  The Ministry of European Funds green-lights the submission of requests for EU funds contribution (from ERDF from SOP-T 2007 - 2013) for the following road rehabilitation projects part of the Roads 6 programme:
Thus, these three Roads 6 projects in northwestern Romania are to increase the absorption of EU funds through the SOP-T 2007 - 2013 by roughly 117 MEUR.
06/15 (http://forum.peundemerg.ro/index.php?topic=12.msg120264#msg120264)  Construction pics from the modernisation of DN 18 between Baia Mare and Sighetu Marmației (contract 6R11).
06/28 (http://forum.peundemerg.ro/index.php?topic=12.msg121402#msg121402)  Progress regarding the rehabilitation of DN 76, according to a press release (http://www.cnadnr.ro/docs/comunicate/Comunicat%20CNADNR%20SA%2028.06.pdf) from RNCMNR:
06/28 (http://forum.peundemerg.ro/index.php?topic=12.msg121426#msg121426)  Construction permit is issued for the remaining works on the DN 76 section Șoimuș - Brad (see above).
06/30 (http://forum.peundemerg.ro/index.php?topic=12.msg121626#msg121626)  Pictures from a road safety improvement contract on DN 1 between Turda and Cluj-Napoca. There are many views on the forum that these works actually reduce the safety in the respective areas.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on July 02, 2016, 02:10:45 AM
June 2016 * Bypasses

06/08 (http://forum.peundemerg.ro/index.php?topic=7.msg119441#msg119441)  Pics and disappointment regarding the lack of progress on the 4-lane widening of the traffic-choked Bucharest ringroad (section between DN 7 and A1).
06/08  Pictures (http://forum.peundemerg.ro/index.php?topic=7.msg119474#msg119474) show that there are no significant works ongoing on the Carei bypass construction site.
06/10 (http://forum.peundemerg.ro/index.php?topic=7.msg119829#msg119829)  No progress on the construction site of the Tecuci bypass (second section, DN 24 - DN 25).
06/11  Additional pictures (http://forum.peundemerg.ro/index.php?topic=7.msg119963#msg119963) from the Carei bypass construction site, focused on the structure over the railway Carei - Tășnad.
06/23 (http://forum.peundemerg.ro/index.php?topic=7.msg120937#msg120937)  The Târgu Mureș City Hall has prepared feasibility studies for a 2x2 southern bypass that is to connect the A3 motorway connector west of Târgu Mureș to the western end of the Târgu Mureș (DN 13 - DN 15) eastern bypass, currently under construction.
06/25 (http://forum.peundemerg.ro/index.php?topic=7.msg121111#msg121111)  Construction progress according to the official RNCMNR June report for bypasses. Listed below (in order of progress evolution) are only the projects for which some progress was recorded :
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on July 02, 2016, 02:35:44 AM
Câteva idei, prima pornind de la o postare a lui @TibiV:

Quote from: TibiV on July 01, 2016, 02:17:10 AM
Quote from: north on July 01, 2016, 01:52:38 AM

06/13  Impressive video (http://forum.peundemerg.ro/index.php?topic=6.msg120127#msg120127) showing extreme construction mobilization for the km 9 cut section of the Gilău - Nădășel motorway.

Nu stiu daca nu eforturile colegilor nu ar merita ceva de genul:
06/13  Impressive video (http://forum.peundemerg.ro/index.php?topic=6.msg120127#msg120127) showing extreme construction mobilization for the km 9 cut section of the Gilău - Nădășel motorway.

1. În elaborarea acestor sinteze mi-am impus să evit emiterea de judecăți / evaluări a conținutului postărilor, urmărind doar sintetizarea acestora într-un mod (vreau să cred eu) obiectiv. În mod specific, am evitat formule de genul "great pictures" / "great videos".
Privind ceea ce ai propus tu să fie subliniat (cu caractere roșii) mai sus, știu că este vorba de un videoclip cu totul deosebit pentru construcția de autostrăzi în România, pe care majoritatea dintre noi l-am văzut și poate răs-revăzut... Dar pentru motivul expus mai sus nu consider că ar trebui să fie scos în evidență.
Am folosit caractere aldine pentru demararea de licitații / atribuiri de contracte / semnări de contracte / emiterea de ordine de începere (și când o fi cazul deschideri pentru trafic). Dar aș evita să scoatem în evidență un anume video / set de poze / postare analitică în detrimentul altora. Și așa poate unii vor considera că am greșit omițând anumite seturi (scurte) de poze sau anumite postări de analiză / sinteză etc.

2. Apreciez orice mesaje prin PM privind greșeli de ortografie / redactare, eventual omiterea unor idei prezentate în orice thread sintetizat. Cu siguranță că sintezele pot fi îmbunătățite, dar a nu se uita că ele necesită alocarea unei resurse de timp semnificative (de exemplu pentru sintezele pe iunie: cam 6 ore).

3. Rapoartele lunare ale CNADNR privind progresul proiectelor sunt șterse în fiecare lună și înlocuite cu cel mai nou. Ca atare deja legăturile din postările de sinteză din mai sunt perimate. Ar trebui să salvăm rapoartele pe forum.

4. Mă gândesc că, parte din această sinteză, am putea realiza un fel de "tablou de bord" pentru toate proiectele în derulare, prezentând progresul și scoțând în evidență problemele încă nerezolvate de administrație. Ar însemna probabil încă vreo 2 ore de muncă în fiecare lună, dar ar putea fi util pentru comunicarea API - autorități...
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on August 06, 2016, 02:48:54 AM
July 2016 * Motorways: plans and projects

07/10 (http://forum.peundemerg.ro/index.php?topic=9.msg122450#msg122450)  List of major road projects included in the Territorial Development Strategy of Romania (SDTR) up to 2035 (link to the strategy itself here (http://www.mdrap.ro/userfiles/Anexa1(1).doc)). There appears to be a slight incongruence between the SDTR and the GTMP regarding motorway construction priorities.
07/13 (http://forum.peundemerg.ro/index.php?topic=9.msg122659#msg122659)  Legitimate disappointment is expressed about the lack of progress regarding the preparation of studies for other motorway/expressway projects, especially about the delay in retendering the preparation of the priority sections of A7/DX7 that is to connect Moldova (northeastern Romania) to Bucharest.
07/30 (http://forum.peundemerg.ro/index.php?topic=9.msg124347#msg124347)  According to prediction of forum users, no motorway sections are expected to be open to traffic this calendar year.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on August 06, 2016, 02:49:31 AM
July 2016 * A1 Bucharest - Nădlac

07/03 (http://forum.peundemerg.ro/index.php?topic=2.msg121852#msg121852)  (and continued here (http://forum.peundemerg.ro/index.php?topic=2.msg121880#msg121880) and then here (http://forum.peundemerg.ro/index.php?topic=2.msg122036#msg122036)) Many construction pics from Lugoj - Deva motorway, followed by description of ongoing works - still hampered in many locations by the lack of environmental and construction permits, as well as land acquisition issues.
07/08 (http://forum.peundemerg.ro/index.php?topic=2.msg122313#msg122313)  The chronicle of an unbelievable "bureaucratic saga" (2010 - 2016) regarding the "Tunel" cave populated by (protected) bats, and its impact on the construction of the Lugoj - Deva motorway section 4 – apparently a major waste of time and money.
07/08 (http://forum.peundemerg.ro/index.php?topic=2.msg122324#msg122324)  Offers submitted for the tender regarding the acquisition of construction materials / rental services related to the reconstruction of the Orăștie - Sibiu motorway section 3 (km 60+545 - km 60+770), managed in-house by the RNCMNR.
07/14 (http://forum.peundemerg.ro/index.php?topic=2.msg122736#msg122736)  Aerial pictures show no reconstruction works on the closed-to-traffic section of the Orăștie - Sibiu motorway.
07/17 (http://forum.peundemerg.ro/index.php?topic=2.msg122971#msg122971)  Pictures taken from DN 68A showing construction progress for Lugoj - Deva motorway section 3. Followed by picture set (http://forum.peundemerg.ro/index.php?topic=2.msg122973#msg122973) showing progress on the Ilia railway overpass, as well as many other locations on the motorway alignment (sections 3 and 4).
07/18 (http://forum.peundemerg.ro/index.php?topic=2.msg123047#msg123047)  Works advance on Lugoj - Deva motorway section 4, according to a set of pics posted by the RNCMNR...
07/18 (http://forum.peundemerg.ro/index.php?topic=2.msg123058#msg123058)  ... same appears to be true for section 2 of the motorway.
07/19 (http://forum.peundemerg.ro/index.php?topic=2.msg123257#msg123257)  Data from the official RNCMNR July report regarding the status of Lugoj - Deva sections 2, 3 and 4 (currently the only sections under construction part of A1): construction status is at 42.64% for Section 2 (40.95% in the previous month); 55.54% for Section 3 (51.48% in the previous month) and 47.28% for Section 4 (47.12% in the previous month).
07/19 (http://forum.peundemerg.ro/index.php?topic=2.msg123262#msg123262)  An overview of project progress rates shows a rather disappointing evolution during the last 4 months (March to July 2016): 5.04% for Section 2, 16.42% for Section 3 and 3.05%(!) for Section 4 for the Lugoj – Deva motorway.
07/20 (http://forum.peundemerg.ro/index.php?topic=2.msg123342#msg123342)  Few construction pictures from Lugoj - Deva motorway Section 3.
07/20 (http://forum.peundemerg.ro/index.php?topic=2.msg123366#msg123366)  Final acceptance upon completion of works for the Arad - Timișoara motorway. Opened to traffic in 2011, there is controversy regarding the quality of this motorway section (see press article linked in post as well as following posts)...
07/26 (http://forum.peundemerg.ro/index.php?topic=2.msg123894#msg123894)  ... dash-cam videos of this section (for each carriageway) have been recorded and posted this month, to confirm or infirm the statement above.
07/28 (http://forum.peundemerg.ro/index.php?topic=2.msg124187#msg124187)  Pictures showing some progress regarding the construction of the Lugoj - Deva motorway section 4.
07/30 (http://forum.peundemerg.ro/index.php?topic=2.msg124319#msg124319)  Link to aerial video showing sliding on hill adjacent to the Aciliu cut, on the Orăștie - Sibiu motorway section 3 (currently closed to traffic).
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on August 06, 2016, 02:50:36 AM
July 2016 * A3 Bucharest - Borș

07/01 (http://forum.peundemerg.ro/index.php?topic=6.msg121639#msg121639)  The General Director of the RNCMNR states that he expects that construction of section 5 of the Comarnic - Brașov motorway is to be awarded within ~1 month [did not happen!] and that sections 1 through 4 are to be built by using Red FIDIC contracts.
07/04 (http://forum.peundemerg.ro/index.php?topic=6.msg121904#msg121904)  No environmental / construction permits issued yet for the Bucharest sector of the A3. Commencement of works in Septemeber 2016 appears to be an optimistic assumption.
07/04 (http://forum.peundemerg.ro/index.php?topic=6.msg122172#msg122172)  Digression regarding the risks and disadvantages of pushing for the start of construction works without an advance payment.
07/13 (http://forum.peundemerg.ro/index.php?topic=6.msg122714#msg122714)  Construction permit is out for the remaining sector of the Gilău - Nădășel motorway, namely regarding the Nădășel interchange.
07/14 (http://forum.peundemerg.ro/index.php?topic=6.msg122759#msg122759)  Link to four pictures showing progress on the Gilău - Nădășel motorway.
07/14 (http://forum.peundemerg.ro/index.php?topic=6.msg122794#msg122794)  Report (followed by pics) regarding preparation of construction works for one section of the Câmpia Turzii - Târgu Mureș motorway.
07/14 (http://forum.peundemerg.ro/index.php?topic=6.msg122832#msg122832)  Advance payment confirmed for contractor of the Suplacu de Barcău - Borș A3 motorway section.
07/19 (http://forum.peundemerg.ro/index.php?topic=6.msg123183#msg123183)  Press release (http://www.digi24.ro/Stiri/Digi24/Economie/Stiri/Autostrada+in+paragina+Suplacu+de+Barcau+Bors+a+fost+luata+la+pu) implies that checks and requirements of the State Construction Inspectorate are to delay the start of construction for the (partially constructed / abandoned) Suplacu de Barcău - Borș motorway.
07/19 (http://forum.peundemerg.ro/index.php?topic=6.msg123227#msg123227)  Aerial construction video shows quite some progress on the construction of the Gilău - Nădășel A3 motorway section, however to be unusable unless the Someș bridge near Gilău is to be finalised (and tender not yet started).
07/19 (http://forum.peundemerg.ro/index.php?topic=6.msg123252#msg123252)  Construction progress for the Gilău - Nădășel section advanced significantly during the last month, from 74.34% to 77.4%.
07/19 (http://forum.peundemerg.ro/index.php?topic=6.msg123254#msg123254)  All permits have been provided for the construction of the Gilău - Nădășel motorway, and there is nothing holding back this project; motorway expected to be fully functional by December, some adjacent works to extend up to March 2017.
07/20 (http://forum.peundemerg.ro/index.php?topic=6.msg123360#msg123360)  Aerial video showing future alignment of A3 motorway between the Bucharest bypass and Bucharest. No actual construction works are taking place.
07/20 (http://forum.peundemerg.ro/index.php?topic=6.msg123380#msg123380)  Pictures showing preparatory works on some sections of the Câmpia Turzii - Târgu Mureș A3 motorway.
07/24 (http://forum.peundemerg.ro/index.php?topic=6.msg123668#msg123668)  An interchange at the northern end of the Gilău - Mihăiești A3 motorway section (construction contract awarded, some preparatory works started) could provide (assuming the rehabilitation / modernisation of some existing county / communal roads) a rather direct link to DN 1C between Cluj-Napoca and Gherla / Dej / Bistrița.
07/25 (http://forum.peundemerg.ro/index.php?topic=6.msg123825#msg123825)  Although 3.5 months have passed since the termination of the contract regarding the design&build of the Ungheni - Târgu Mureș motorway section, the RNCMNR has not yet retendered this section (the easternmost part of the Câmpia Turzii - Târgu Mureș motorway) - despite the fact that there appear to be no reasons to further delay this project.
07/27 (http://forum.peundemerg.ro/index.php?topic=6.msg124059#msg124059)  A Government Decision regarding land acquisition for the alignment of the Nădășel - Mihăiești motorway section (Red FIDIC construction contract signed, no notice to commence works issued yet) has been subjected to public debate.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on August 06, 2016, 02:51:03 AM
July 2016 * A7 Ploiești - Bacău - Siret

07/14 (http://forum.peundemerg.ro/index.php?topic=58.msg122824#msg122824)  All major bureaucratic stages have been successfully completed for the Bacău motorway bypass (mainly environmental and construction permit), however no significant (pre)construction activities appear to be taking place yet.
07/17 (http://forum.peundemerg.ro/index.php?topic=58.msg122968#msg122968)  Archaeological clearance has been started for the Bacău bypass.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on August 06, 2016, 02:51:27 AM
July 2016 * A10 Sebeș - Turda

07/02 (http://forum.peundemerg.ro/index.php?topic=165.msg121778#msg121778)  (and subsequent posts) [Re]mobilisation for works on sections 1, 2 and 3.
07/05 (http://forum.peundemerg.ro/index.php?topic=165.msg121984#msg121984)  Construction permit for section 4 has been issued...
07/05 (http://forum.peundemerg.ro/index.php?topic=165.msg122005#msg122005)  ...however excluding minor sectors with additional land acquisition required: km 53+700 - km 53+900 (Unirea interchange), DC 85 motorway bridge and sector near Stejeriș lake.
07/07  (also subsequent posts) Construction site report and pics (http://forum.peundemerg.ro/index.php?topic=165.msg122247#msg122247) from section 2, showing mainly work at structures.
07/08 (http://forum.peundemerg.ro/index.php?topic=165.msg122316#msg122316)  Remobilisation noticed (earthwork pics) on section 3.
07/11 (http://forum.peundemerg.ro/index.php?topic=165.msg122516#msg122516)  Press article (http://alba24.ro/foto-autostrada-sebes-turda-cum-se-lucreaza-dupa-autorizarea-pe-loturi-santierele-de-langa-alba-iulia-si-celelalte-zone-505317.html) (includes pictures from the forum) showing progress of works after construction permits were issued.
07/12 (http://forum.peundemerg.ro/index.php?topic=165.msg122596#msg122596)  An additional construction permit is issued for section 4.
07/13 (http://forum.peundemerg.ro/index.php?topic=165.msg122652#msg122652)  Critical analysis regarding construction status of the Turda - Sebeș motorway sections, outlining critical construction points for sections 3 and 4.
07/14 (http://forum.peundemerg.ro/index.php?topic=165.msg122799#msg122799)  Photo report showing that [re]mobilisation is still ongoing for all sections, works still far from advancing at full throttle.
07/17 (http://forum.peundemerg.ro/index.php?topic=165.msg122960#msg122960)  Construction site pics from section 2.
07/20 (http://forum.peundemerg.ro/index.php?topic=165.msg123272#msg123272)  Official construction progress from June to July: Section 1: 12.55% to 12.69%; Section 2: 9.28% to 9.43%; Section 3: remains at 48.68%; Section 4: remains at 47.50%.
07/21 (http://forum.peundemerg.ro/index.php?topic=165.msg123470#msg123470)  Rather disappointing construction update report, especially regarding lack of progress on sections 1 and 4.
07/22 (http://forum.peundemerg.ro/index.php?topic=165.msg123595#msg123595)  Construction pics from section 2.
07/23 (http://forum.peundemerg.ro/index.php?topic=165.msg123617#msg123617)  Pictures showing that apparently no significant works are taking place on section 1.
07/26 (http://forum.peundemerg.ro/index.php?topic=165.msg124019#msg124019)  Pics showing progress regarding installation of beams on structure at km 51+450 of Section 3.
07/28 (http://forum.peundemerg.ro/index.php?topic=165.msg124215#msg124215)  It appears that additional archaeological sites of major importance have been identified on the motorway alignment.
07/29 (http://forum.peundemerg.ro/index.php?topic=165.msg124229#msg124229)  Pics showing (mostly) alignment + some works on Section 1. Also see additional posts (http://forum.peundemerg.ro/index.php?topic=165.msg124278#msg124278) on the same topic.
07/30 (http://forum.peundemerg.ro/index.php?topic=165.msg124349#msg124349)  Construction pics showing progress on Section 4.
07/31 (http://forum.peundemerg.ro/index.php?topic=165.msg124370#msg124370) (also see 07/30 (http://forum.peundemerg.ro/index.php?topic=165.msg124313#msg124313))  Comparison of changes regarding alignment and interchange placement / configuration between the feasibility studies for the Turda - Sebeș expressway (2007 - 2008) and the Sebeș - Turda motorway (update 2013).
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on August 06, 2016, 02:51:49 AM
July 2016 * National roads

07/01 (http://forum.peundemerg.ro/index.php?topic=12.msg121717#msg121717)  Site pics from DN 18 Moisei - Iacobeni: still to be modernised under the (only failed) Roads 6 contract, 6R16.
07/06 (http://forum.peundemerg.ro/index.php?topic=12.msg122119#msg122119)  DN 14A between Mediaș and county limit SB/MS receives a much-awaited wearing asphalt layer.
07/08 (http://forum.peundemerg.ro/index.php?topic=12.msg122273#msg122273)  Dash-cam video of DN 66 Târgu Jiu - Petroșani, showing progress on the Roads V rehabilitation contract 5R3 Bumbești Jiu - Petroșani.
07/15 (http://forum.peundemerg.ro/index.php?topic=12.msg122895#msg122895)  Table showing AADT 2015/2010 change for all national in Romania (however not section-based, but only road number-based).
07/19 (http://forum.peundemerg.ro/index.php?topic=12.msg123226#msg123226)  Road recycling technology used in the northern part of the country for rehabilitating 13.5 km of DN 17C and 21.5 km of DN 17D - construction permits have just been issued.
07/20 (http://forum.peundemerg.ro/index.php?topic=12.msg123382#msg123382)  Road safety improvement projects (such as this one on DN 1 Turda - Cluj-Napoca) are criticised for actually increasing risk of accidents.
07/23 (http://forum.peundemerg.ro/index.php?topic=12.msg123597#msg123597)  Pictures showing progress regarding the modernisation of DN 76 between Vârfurile and Ștei.
07/24 (http://forum.peundemerg.ro/index.php?topic=12.msg123669#msg123669)  Map showing graphical representation of 2015/2010 AADT variation data from 07/15 post above...
07/26 (http://forum.peundemerg.ro/index.php?topic=12.msg123880#msg123880)  ...followed by same for heavy traffic + discussion.
07/30 (http://forum.peundemerg.ro/index.php?topic=12.msg124328#msg124328)  Many pictures showing progress of road modernisation of DN 5 Bucharest - Adunații Copăceni, a project that has been lagging for over a decade.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on August 06, 2016, 02:52:10 AM
July 2016 * Bypasses

07/01 (http://forum.peundemerg.ro/index.php?topic=7.msg121696#msg121696)  Construction permit issued for widening of Bucharest bypass between A1 and DN 7 regarding change of a technical solution on this sector.
07/06  Acquisition of additional plots for the widening of the Brașov bypass (http://forum.peundemerg.ro/index.php?topic=7.msg122129#msg122129) (sector DN 11 - DN 13) as well as for the Carei bypass (http://forum.peundemerg.ro/index.php?topic=7.msg122147#msg122147).
07/06 (http://forum.peundemerg.ro/index.php?topic=7.msg122150#msg122150)  Aerial video of the works for the widening of the Bucharest bypass between A1 and DN 7. Much still needs to be done to finalise this highly important project.
07/08 (http://forum.peundemerg.ro/index.php?topic=7.msg122359#msg122359)  Few pictures from the Caracal bypass construction site.
07/13 (http://forum.peundemerg.ro/index.php?topic=7.msg122675#msg122675)  Limited progress regarding the preparation of three much-awaited improvements on the 4-lane section of the Bucharest north bypass (i.e. the construction of a roundabout at its intersection with DJ 200B Pipera - Tunari; the provision of pedestrian overpasses on the sector between DN 1A and DN 1; increasing the capacity of the DN 1 (northbound) -> Bucharest bypass ramp at the DN 1 / bypass interchange).
07/17 (http://forum.peundemerg.ro/index.php?topic=7.msg122956#msg122956)  Pictures showing start of works for the construction of the Târgu Mureș bypass.
07/20 (http://forum.peundemerg.ro/index.php?topic=7.msg123312#msg123312)  Construction progress according to the official RNCMNR July report for bypasses. Listed below (in order of progress evolution) are only the four projects for which some progress was recorded :
07/25 (http://forum.peundemerg.ro/index.php?topic=7.msg123816#msg123816)  Construction pictures from two grade-separation projects on the Oradea bypass, at the Ciheiului and Nojoridului streets (see map here (https://www.google.ro/maps/@47.0305685,21.9364281,15.5z))...
07/26 (http://forum.peundemerg.ro/index.php?topic=7.msg123891#msg123891)  ...officially to be finished in November 2016.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on September 05, 2016, 02:50:01 AM
August 2016 * Motorways: plans and projects

08/24 (http://forum.peundemerg.ro/index.php?topic=9.msg126589#msg126589)  Except for the preparation of the FS for the Sibiu – Pitești motorway, no other major road projects are being prepared at this moment*) - and no other FS studies are even under tender; as per posting user: "Have we all went crazy?" It is thus unlikely that up until 2020 we will see any other new projects started...
08/24 (http://forum.peundemerg.ro/index.php?topic=9.msg126594#msg126594)  ...however, a FS contract for the Sibiu - Făgăraș motorway has been signed but then suspended for one year in 11/2015.

*) Except the A3 sections between Mihăiești and Suplacu de Barcău.

[Also a relevant and somewhat connected post from the EU funds absorption thread quoted below]
08/04 (http://forum.peundemerg.ro/index.php?topic=294.msg124704#msg124704)  A rather salient point is made: given the disastrous EU funds absorption rate for the 2007 - 2013 period, we should not wait for the approval of the GTMP, but rather seek to start as many projects as possible (with financing from the state budget, EIB/EBRD loans etc.) and then seeking approval for retroactive co-financing from EU funds.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on September 05, 2016, 02:50:29 AM
August 2016 * A1 Bucharest - Nădlac

08/02 (http://forum.peundemerg.ro/index.php?topic=2.msg124607#msg124607)  RNCMNR staff from the Cluj regional office have been mobilised in order to start reconstructing the Orăștie - Sibiu motorway section 3 (km 60+545 - km 60+770), currently closed to traffic for almost one year.
08/05 (http://forum.peundemerg.ro/index.php?topic=2.msg124842#msg124842)  [and subsequent posts] Many, many pics showing somewhat limited progress on Lugoj - Deva motorway section 4, however much better progress on section 3.
09/08 (http://forum.peundemerg.ro/index.php?topic=2.msg125222#msg125222)  RNCMNR technical committee decided on the technical solution to be implemented for the reconstruction of the Orăștie - Sibiu motorway section 3 (km 60+545 - km 60+770).
08/11 (http://forum.peundemerg.ro/index.php?topic=2.msg125365#msg125365)  First report about the commencement of works for the reconstruction of the above-mentioned motorway section (later followed by pics (http://forum.peundemerg.ro/index.php?topic=2.msg125452#msg125452), also see subsequent posts).
08/14 (http://forum.peundemerg.ro/index.php?topic=2.msg125618#msg125618)  Pictures from the Margina interchange on Lugoj - Deva motorway section 2 (and other sites from the same section in the subsequent post)...
08/15 (http://forum.peundemerg.ro/index.php?topic=2.msg125658#msg125658)  ...however, despite this being the section with the earliest expected opening (this is valid only for the Dumbrava - Margina subsection), there are still permitting issued to be solved (renewed Environmental Permit + Construction Permit for additional sites).
08/15 (http://forum.peundemerg.ro/index.php?topic=2.msg125686#msg125686)  An underpass on the Lugoj - Deva motorway section 3 (serving national road 68A), which was supposed to have an overhead clearance of 5 m, was built with a clearance of only 4.81 m at one of its ends, which lead to an excavator becoming stuck in the underpass. Picture shows corrective reconstruction undertaken: depressing the national road.
08/17 (http://forum.peundemerg.ro/index.php?topic=2.msg125876#msg125876)  Works on the reconstruction of the Orăștie - Sibiu motorway section 3 (km 60+545 - km 60+770) have finally begun!...
08/18 (http://forum.peundemerg.ro/index.php?topic=2.msg126030#msg126030)  ...to be finalised by mid/end September.
08/19 (http://forum.peundemerg.ro/index.php?topic=2.msg126096#msg126096)  A (long) list of client-side problems regarding the construction of the Lugoj - Deva motorway section 4. It includes missing environmental permit, construction permits, land acquistion and problems with utilities relocation.
08/21 (http://forum.peundemerg.ro/index.php?topic=2.msg126257#msg126257)  (and subsequent posts) Avalanche of pics from all three Lugoj - Deva motorway sections under construction.
08/23 (http://forum.peundemerg.ro/index.php?topic=2.msg126485#msg126485)  Video showing reconstruction works for the Orăștie - Sibiu motorway section 3 (km 60+545 - km 60+770).
08/25 (http://forum.peundemerg.ro/index.php?topic=2.msg126737#msg126737)  RNCMNR informs about progress regarding geotechnical investigations on the Sibiu - Pitești motorway. Progress for geotechnical boring stands at 75% (Section 1 Sibiu – Boița), 35% (Section 4 Văleni – Curtea de Argeș) and 80% (Section 5 Curtea de Argeș – Pitești); pictures included.
08/26 (http://forum.peundemerg.ro/index.php?topic=2.msg126855#msg126855)  Data from the official RNCMNR July report regarding the status of Lugoj - Deva sections 2, 3 and 4 (currently the only sections under construction part of A1): construction status is at 45.22% for Section 2 (42.64% in July); 60.86% for Section 3 (55.54% in July) and 47.92% for Section 4 (47.28% in July). It is to be noted that Section 2 has advanced during the last month (5.32%) more than it has advanced during the previous four months (http://forum.peundemerg.ro/index.php?topic=446.msg124870#msg124870) (March - July) (5.04%).
08/30 (http://forum.peundemerg.ro/index.php?topic=2.msg127295#msg127295)  Pictures showing the critical points on the Lugoj - Deva motorway section 3...
08/30 (http://forum.peundemerg.ro/index.php?topic=2.msg127314#msg127314)  ...followed by brief analysis about the feasibility of opening to traffic this year of the section Ilia - Grind.
08/30 (http://forum.peundemerg.ro/index.php?topic=2.msg127323#msg127323)  Aerial video of the Lugoj - Deva sections 4 and 3, followed by the following two comments:
08/31 (http://forum.peundemerg.ro/index.php?topic=2.msg127347#msg127347)  Aerial video of the Lugoj - Deva section 2, subsection Dumbrava - Margina. This is the only motorway section with a reasonable probability of opening this year.
08/31 (http://forum.peundemerg.ro/index.php?topic=2.msg127383#msg127383)  Progress achieved on Section 2 during the last two months is shown by comparing corresponding stills from videos.
08/31 (http://forum.peundemerg.ro/index.php?topic=2.msg127426#msg127426)  Video showing reconstruction works for Orăștie - Sibiu motorway section 3 (km 60+545 - km 60+770).
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on September 05, 2016, 02:50:54 AM
August 2016 * A3 Bucharest - Borș

08/01 (http://forum.peundemerg.ro/index.php?topic=6.msg124496#msg124496)  Pictures showing the alignment of the southernmost section of the A3 motorway, near Bucharest. No works taking place yet.
08/05 (http://forum.peundemerg.ro/index.php?topic=6.msg124854#msg124854)  Major earthworks taking place at the site of the massive cut in the forest area near Nădășel.
08/06 (http://forum.peundemerg.ro/index.php?topic=6.msg124949#msg124949)  Pictures proving that clearing and grubbing, as well as other construction activities have started on the Ungheni - Ogra section of the Târgu Mureș - Câmpia Turzii motorway.
08/12 (http://forum.peundemerg.ro/index.php?topic=6.msg125519#msg125519)  Pictures: works advancing quickly on the northern part of the Gilău - Nădășel motorway.
08/14 (http://forum.peundemerg.ro/index.php?topic=6.msg125614#msg125614)  According to a forum user, the general director of the RNCMNR has declared on national TV that in September we will have contractors assigned for the construction of sections 1 and 5 of the Predeal - Brașov motorway, as well as for the Bușteni and Comarnic bypasses.
08/15 (http://forum.peundemerg.ro/index.php?topic=6.msg125679#msg125679)  The very first aerial video showing the site as well as some incipient construction works on the Târgu Mureș - Câmpia Turzii motorway, subsections between Ungheni and Iernut!
08/15 (http://forum.peundemerg.ro/index.php?topic=6.msg125696#msg125696)  Dissatisfaction is mounting towards RNCMNR's impotence in retendering the terminated Târgu Mureș - Ungheni motorway contract, as well as the tendering of the remaining works for the Gilău Someș river bridge / viaduct.
08/16 (http://forum.peundemerg.ro/index.php?topic=6.msg125806#msg125806)  Amazing aerial video of the ongoing works on the entire Gilău - Nădășel motorway (dated 08/13).
08/18 (http://forum.peundemerg.ro/index.php?topic=6.msg125980#msg125980)  An ongoing dispute between the RNCMNR and the national authority for overseeing public tenders regarding the feasibility study for the Comarnic - Brașov motorway (except sections 1 and 5) appears to be pushing towards the contracting of the feasibility study,
08/19 (http://forum.peundemerg.ro/index.php?topic=6.msg126083#msg126083)  User documents the start of archaeological clearance works for the Nădășel - Mihăiești A3 motorway section.
08/21 (http://forum.peundemerg.ro/index.php?topic=6.msg126237#msg126237)  Pictures showing preparatory works for major structures on the Iernut - Chețani motorway section.
08/22 (http://forum.peundemerg.ro/index.php?topic=6.msg126387#msg126387)  User reports restart of works for the southernmost section of the A3 motorway, near Bucharest...
08/23 (http://forum.peundemerg.ro/index.php?topic=6.msg126456#msg126456)  ...with confirmation from local press article (http://www.click.ro/news/national/dat-domnul-se-lucreaza-la-autostrada-bucuresti-ploiesti).
08/26 (http://forum.peundemerg.ro/index.php?topic=6.msg126815#msg126815)  The local EPA's have decided for a full environmental assessment for the Ogra - Borș A3 motorway sector. Thus, it will take quite some time for the environmental permit to be issued.
08/27 (http://forum.peundemerg.ro/index.php?topic=6.msg127001#msg127001)  Drone-recorded video showing some preparatory works for the largest structure on the future Târgu Mureș - Câmpia Turzii motorway: the Bogata viaduct/bridge.
08/27 (http://forum.peundemerg.ro/index.php?topic=6.msg127040#msg127040)  Aerial video showing construction activities (mostly access roads, clearing & grubbing, as well as excavation and some drilling for structures) from the Ungheni - Ogra motorway.
08/29 (http://forum.peundemerg.ro/index.php?topic=6.msg127211#msg127211)  User points out that still no notice to commence has been issued for the Nădășel - Mihăiești motorway section (D&B contract signed on 05/26 this year). From that point on, six months of design activities are to follow.
08/30 (http://forum.peundemerg.ro/index.php?topic=6.msg127291#msg127291)  Impressive start of construction activities on the Ungheni - Ogra motorway section (consortium lead by Strabag) is reported. Few pictures showing clearing and grubbing + excavation.
08/31 (http://forum.peundemerg.ro/index.php?topic=6.msg127351#msg127351)  A government decision should be soon issued regarding land acquisition for the Nădășel - Mihăiești motorway section. This does not include "additional plots" as needed according to the detailed design (to be realised at some point in the future). This was indeed adopted (http://gov.ro/ro/guvernul/sedinte-guvern/informatie-de-presa-privind-proiecte-i-acte-normative-adoptate-in-sedinta-guvernului-romaniei-din-31-08-2016) by the government during the cabinet meeting on 08/31.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on September 05, 2016, 02:51:26 AM
August 2016 * A7 Ploiești - Bacău - Siret

08/15 (http://forum.peundemerg.ro/index.php?topic=58.msg125741#msg125741)  Ample set of pictures showing future construction site and some preparatory / mobilisation works for the Bacău motorway bypass.
08/23 (http://forum.peundemerg.ro/index.php?topic=58.msg126697#msg126697)  Advance payment (of 70.9 million RON) for the Bacău bypass has been paid.
08/25 (http://forum.peundemerg.ro/index.php?topic=58.msg126729#msg126729)  User reports progress of the archaeological clearance procedure for the Bacău bypass.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on September 05, 2016, 02:51:45 AM
August 2016 * A10 Sebeș - Turda

08/01 (http://forum.peundemerg.ro/index.php?topic=165.msg124499#msg124499)  Some clearing and grubbing works reported for Section 1 (pictures)...
08/03 (http://forum.peundemerg.ro/index.php?topic=165.msg124645#msg124645)  ...as well as preparatory works for the same section (relocation of county road 107 east of Alba Iulia).
08/04 (http://forum.peundemerg.ro/index.php?topic=165.msg124695#msg124695)  (and subsequent posts) Pictures from sections 2, 3, 4 of the motorway.
08/04 (http://forum.peundemerg.ro/index.php?topic=165.msg124709#msg124709)  Pics showing additional mobilisation on Section 1.
08/05 (http://forum.peundemerg.ro/index.php?topic=165.msg124780#msg124780)  Multiple users confirm heavy traffic and major delays on parallel national road DN 1 between Sebeș and Turda, wishing for the motorway to become functional as soon as possible.
08/07 (http://forum.peundemerg.ro/index.php?topic=165.msg124974#msg124974)  Even more pictures proving remobilisation on Section 1.
08/07 (http://forum.peundemerg.ro/index.php?topic=165.msg124978#msg124978)  Construction site pics from Section 3.
08/09 (http://forum.peundemerg.ro/index.php?topic=165.msg125220#msg125220)  Pictures to show additional mobilisation on Section 1.
08/11 (http://forum.peundemerg.ro/index.php?topic=165.msg125402#msg125402)  Aerial video of the entire future A10 from Turda to Sebeș.
08/12 (http://forum.peundemerg.ro/index.php?topic=165.msg125512#msg125512)  "Insider" forum member presents unfair situation regarding compensations for land acquisition on the motorway proper.
08/16 (http://forum.peundemerg.ro/index.php?topic=165.msg125801#msg125801)  It appears that end of 2017 is an optimistic deadline for the opening of section 2 of the motorway...
07/16 (http://forum.peundemerg.ro/index.php?topic=165.msg125815#msg125815)  ...(same user states that) 2018 appears to be a realistic deadline for section 2; for section 1 - it remains to be seen.
08/17 (http://forum.peundemerg.ro/index.php?topic=165.msg125886#msg125886)  User expresses his disappointment regarding remobilisation of works on section 4 and especially on section 3...
08/17 (http://forum.peundemerg.ro/index.php?topic=165.msg125944#msg125944)  ...followed by pics to prove it.
08/22 (http://forum.peundemerg.ro/index.php?topic=165.msg126332#msg126332)  Pictures from the A10 / A3 interchange.
08/22 (http://forum.peundemerg.ro/index.php?topic=165.msg126382#msg126382)  Pictures from Sections 2 and 3.
08/24 (http://forum.peundemerg.ro/index.php?topic=165.msg126574#msg126574)  Still no proper mobilisation for construction of Sections 2, 3 and 4.
08/26 (http://forum.peundemerg.ro/index.php?topic=165.msg126888#msg126888)  Pictures showing progress at the Aiud interchange on Section 3 of the motorway.
08/26 (http://forum.peundemerg.ro/index.php?topic=165.msg126893#msg126893)  More pictures showing progress on Section 3.
08/26 (http://forum.peundemerg.ro/index.php?topic=165.msg126906#msg126906)  Aerial video showing the A3-A10 interchange south of Turda. Unfortunately insignificant construction activities are recorded.
08/27 (http://forum.peundemerg.ro/index.php?topic=165.msg126950#msg126950)  Some progress photodocumented for Sections 1 and 2.
08/28 (http://forum.peundemerg.ro/index.php?topic=165.msg127102#msg127102)  More pics from Section 1.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on September 05, 2016, 02:52:04 AM
August 2016 * National roads

08/04 (http://forum.peundemerg.ro/index.php?topic=12.msg124693#msg124693)  Some pictures to present progress on DN 76 section Beiuș - Ștei...
08/04 (http://forum.peundemerg.ro/index.php?topic=12.msg124743#msg124743)  ... as well as section Ștei - Vârfurile.
08/07 (http://forum.peundemerg.ro/index.php?topic=12.msg124970#msg124970)  Technical design for DN 18 Moisei - Cârlibaba (part of the former contract 6R13 from Roads VI programme) have been approved - work should start within weeks.
08/11 (http://forum.peundemerg.ro/index.php?topic=12.msg125428#msg125428)  More pictures from modernisation of DN 76 section Beiuș - Ștei.
08/13 (http://xn--bumbeti%20jiu%20-%20petroani-6jfu)  Pictures showing works on DN 66 Bumbești Jiu - Petroșani (contract 5R3). Note that the finacing contract for this project (as well as DN 76 - and DN 56) was signed 14 years ago with the EIB.
08/17 (http://forum.peundemerg.ro/index.php?topic=12.msg125907#msg125907)  Pics showing progress (or rather lack of progress) on modernisation of the four-lane DN 5 between Bucharest and Adunații Copăceni.
08/24 (http://forum.peundemerg.ro/index.php?topic=12.msg126592#msg126592)  Pictures showing progress on the in situ road recycling-based rehabilitation of DN 17C Bistrița - Năsăud and DN 17D Beclean - Salva - Năsăud.
08/25 (http://forum.peundemerg.ro/index.php?topic=12.msg126702#msg126702)  More pics showing heavy works on the modernisation of DN 76 section Ștei - Vârfurile.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on September 05, 2016, 02:52:41 AM
August 2016 * Bypasses

08/06 (http://forum.peundemerg.ro/index.php?topic=7.msg124910#msg124910)  Ample report (including pics) from the construction site of the Brașov bypass (widening between DN 13 and DN 11 + new construction between DN 11 and existing bypass north of DN 1 / DN 1A interchange).
08/10 (http://forum.peundemerg.ro/index.php?topic=7.msg125314#msg125314)  Update from the Târgu Mureș bypass showing rather limited progress.
08/10 (http://forum.peundemerg.ro/index.php?topic=7.msg125349#msg125349)  More pictures from the widening of the Brașov bypass between DN 11 and DN 13.
08/11 (http://forum.peundemerg.ro/index.php?topic=7.msg125466#msg125466)  Progress recorded for the construction of road bypasses during the last month, as per the official monthly report from the RNCMNR (ordered by progress achieved):
08/18 (http://forum.peundemerg.ro/index.php?topic=7.msg126025#msg126025)  Pictures from the construction of the Târgu Jiu bypass - courtesy of RNCMNR - SDN Târgu Jiu.
08/19 (http://forum.peundemerg.ro/index.php?topic=7.msg126118#msg126118)  Pics showing progress on the Târgu Mureș bypass construction site.
08/22 (http://forum.peundemerg.ro/index.php?topic=7.msg126402#msg126402)  Yet another set of pics from the Brașov bypass widening.
08/22 (http://forum.peundemerg.ro/index.php?topic=7.msg126404#msg126404)  Rather disappointing progress documented for the Târgu Jiu bypass.
08/29 (http://forum.peundemerg.ro/index.php?topic=7.msg127236#msg127236)  Some pictures showing some rather unsatisfactory progress for the Târgu Mureș bypass.
08/30 (http://forum.peundemerg.ro/index.php?topic=7.msg127284#msg127284)  Dash-cam pictures showing some progress at the grade separation projects on the Oradea bypass.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on October 01, 2016, 01:43:17 AM
September 2016 * Motorways: plans and projects

09/01 (http://forum.peundemerg.ro/index.php?topic=9.msg127439#msg127439)  (asp) Discussion anticipating problems on the future missing motorway sections: Sebeș - Aiud and Holdea [or Margina] - Dobra and potential to mitigate traffic problems. Consensus is that the biggest problems will be on the Sebeș - Alba Iulia section as well as inside the Teiuș and Aiud towns. Limited options to temporarily address capacity are identified: signalised pedestrian crossings in Teiuș and Aiud, as well as solving the quality problems of the outermost lanes on the 4-lane section inside Alba Iulia (south).
09/13 (http://forum.peundemerg.ro/index.php?topic=9.msg128602#msg128602)  Link to an article showing the disastrous progress regarding the execution of this year's national roads budget: a total of 4140 MRON was budgeted for 2016 for the RNCMNR, of which the spending in the first part of the year was 762 MRON (18.4%!). Thus a negative budget rectification of 357 MRON was applied by the government.
09/13 (http://forum.peundemerg.ro/index.php?topic=9.msg128674#msg128674)  (asp) Discussion regarding the suboptimal planned links to the national high speed road network of Satu Mare / Baia Mare / Maramureș: via route Baia Mare - Dej instead of Baia Mare - Zalău. Consensus is that the latter would have been preferred.
09/14 (http://forum.peundemerg.ro/index.php?topic=9.msg128828#msg128828)  The GTMP was approved by the government by means of a government decision.
09/18 (http://forum.peundemerg.ro/index.php?topic=9.msg129247#msg129247)  (asp) Discussions about the preferred priority way to continue eastward the (future) west - east motorway axis Timișoara - Brașov: towards Bacău or towards Galați / Brăila.
09/19 (http://forum.peundemerg.ro/index.php?topic=9.msg129307#msg129307)  Two lists providing an overview of ongoing road projects of national importance: those that progress satisfactorily and those - reference made only to projects with already executed works - that are "blocked".
09/21 (http://forum.peundemerg.ro/index.php?topic=9.msg129494#msg129494)  (asp) Discussion on what is currently more suitable for motorway construction in Romania: yellow (D&B) or red (B) FIDIC-type contracts? No clear conclusion drawn.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on October 01, 2016, 01:43:47 AM
September 2016 * A1 Bucharest - Nădlac

09/01 (http://forum.peundemerg.ro/index.php?topic=2.msg127474#msg127474cgf)  Pictures from Lugoj - Deva section 3 (asphalt and finishing works) courtesy of RNCMNR - Timișoara regional office.
09/07 (http://forum.peundemerg.ro/index.php?topic=2.msg128115#msg128115)  (asp) Ample set of pictures covering construction progress on Lugoj - Deva motorway section 4...
09/07 (http://forum.peundemerg.ro/index.php?topic=2.msg128206#msg128206)  ...continues here, also covering section 3.
09/09 (http://forum.peundemerg.ro/index.php?topic=2.msg128357#msg128357)  Section 2 pictures, courtesy of RNCMNR.
09/10 (http://forum.peundemerg.ro/index.php?topic=2.msg128465#msg128465)  Data from the official RNCMNR monthly report regarding the status of Lugoj - Deva sections 2, 3 and 4 (currently the only sections under construction part of A1): construction status is at 46.96% for Section 2 (45.22% in August); 63.24% for Section 3 (60.86% in August) and 47.98% for Section 4 (47.92% in August).
09/11 (http://forum.peundemerg.ro/index.php?topic=2.msg128529#msg128529)  (asp) Sunday pictures from Lugoj - Deva motorway section 2.
09/14 (http://forum.peundemerg.ro/index.php?topic=2.msg128783#msg128783)  (asp) Pictures from Lugoj - Deva motorway section 3.
09/15 (http://forum.peundemerg.ro/index.php?topic=2.msg128838#msg128838)  And yet another set from section 4 of the same motorway. Works appear to be taking place at many sites, despite virtually no advance being seen in the official monthly reports.
09/15 (http://forum.peundemerg.ro/index.php?topic=2.msg128877#msg128877)  (asp) Even many many more pictures from section 3.
09/16 (http://forum.peundemerg.ro/index.php?topic=2.msg129051#msg129051)  (asp) Pictures showing progress for the reconstruction of the Orăștie - Sibiu motorway section 3 (km 60+545 - km 60+770), supposedly to be completed by the end of this month.
09/19 (http://forum.peundemerg.ro/index.php?topic=2.msg129301#msg129301)  According to realistic estimates from forum members, the Lugoj - Deva motorway will only be completed by 2020, namely due to the section featuring tunnels that still needs to be tendered.
09/19 (http://forum.peundemerg.ro/index.php?topic=2.msg129324#msg129324)  Link to press material showing promise from the prime-minister that the section with tunnels will be tendered "during this fall".
09/23 (http://forum.peundemerg.ro/index.php?topic=2.msg129324#msg129324)  In-depth analysis of forum member concludes that the Sibiu - Pitești motorway could open by: 2022 - 2023 (in a very optimistic scenario); 2025 (in a realistic/optimistic scenario); 2030 (in a realistic/pessimistic scenario).
09/25 (http://forum.peundemerg.ro/index.php?topic=2.msg129897#msg129897)  Pictures showing heavy mobilisation for the reconstruction of the Orăștie - Sibiu motorway section 3 (km 60+545 - km 60+770), yet it appears to be unlikely to be opened to traffic by the end of the month.
09/26 (http://forum.peundemerg.ro/index.php?topic=2.msg129946#msg129946)  (asp) Extremely long set of pictures from Lugoj - Deva motorway construction section 4...
09/27 (http://forum.peundemerg.ro/index.php?topic=2.msg130213#msg130213)  ...followed by some pics from section 2.
09/27 (http://forum.peundemerg.ro/index.php?topic=2.msg130221#msg130221)  RNCMNR officially acknowledges that the Orăștie - Sibiu section 3 won't reopen to traffic by the end of the month; blames it on the rain.
09/29 (http://forum.peundemerg.ro/index.php?topic=2.msg130567#msg130567)  Pictures from the subsection of the Lugoj - Deva section 2 motorway that is supposed to open to traffic this year...
09/30 (http://forum.peundemerg.ro/index.php?topic=2.msg130659#msg130659)  (asp) ...and yet another set.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on October 01, 2016, 01:44:08 AM
September 2016 * A3 Bucharest - Borș

09/03 (http://forum.peundemerg.ro/index.php?topic=6.msg127731#msg127731)  Advance payment (of 60.6 million RON) for the Suplacu de Barcău - Borș bypass has been paid to the contractor.
09/05 (http://forum.peundemerg.ro/index.php?topic=6.msg127871#msg127871)  Forum member expresses dissatisfaction with the notice to commence not yet being issued for the section Nădășel - Mihăiești, despite the contract having been signed in May this year.
09/05 (http://forum.peundemerg.ro/index.php?topic=6.msg127945#msg127945)  Pictures showing clearing & grubbing works on the Ungheni - Sânpaul section.
09/08 (http://forum.peundemerg.ro/index.php?topic=6.msg128280#msg128280)  It appears that works have finally restarted (albeit in a timid manner) on the Suplacu de Barcău - Borș section.
09/10 (http://forum.peundemerg.ro/index.php?topic=6.msg128480#msg128480)  According to the RNCMNR's official monthly progress report, the following physical completion rates are recorded for sections currently under construction: Târgu Mureș - Ogra section 2: 3.24%; Gilău - Nădășel: 82%; Suplacu de Barcău - Borș: 52.12%.
09/16 (http://forum.peundemerg.ro/index.php?topic=6.msg129048#msg129048)  (asp) Pictures showing start of works around the Popasului interchange on the Bucharest section of the motorway.
09/17 (http://forum.peundemerg.ro/index.php?topic=6.msg129139#msg129139)  (Mostly) alignment pics from the Suplacu de Barcău - Borș section of the motorway.
09/20 (http://forum.peundemerg.ro/index.php?topic=6.msg129387#msg129387)  Construction pics from the Ogra - Târgu Mureș section.
09/20 (http://forum.peundemerg.ro/index.php?topic=6.msg129425#msg129425)  Aerial video recording of works on the Gilău - Nădășel section.
09/21 (http://forum.peundemerg.ro/index.php?topic=6.msg129599#msg129599)  Aerial video showing some of the works / alignment on the Suplacu de Barcău - Borș section.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on October 01, 2016, 01:44:38 AM
September 2016 * A7 Ploiești - Bacău - Siret

09/08 (http://forum.peundemerg.ro/index.php?topic=58.msg128288#msg128288)  Link to press article quoting the General Director of the RNCMNR stating that the tender for the FS for the Ploiești - Bacău expressway/motorway will be published in the national tender system within two weeks [did not happen!], while the corresponding tender for the remaining section Bacău - Pașcani will "probably" be launched in October.
09/09 (http://forum.peundemerg.ro/index.php?topic=58.msg128393#msg128393)  Pictures showing archaeological clearance works on the Bacău bypass.
09/10 (http://forum.peundemerg.ro/index.php?topic=58.msg128492#msg128492)  (asp) Bacău bypass alignment pictures: clearing & grubbing, preparatory works.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on October 01, 2016, 01:44:57 AM
September 2016 * A10 Sebeș - Turda

09/01 (http://forum.peundemerg.ro/index.php?topic=165.msg127459#msg127459)  Pics with construction activities from section 4.
09/01 (http://forum.peundemerg.ro/index.php?topic=165.msg127508#msg127508)  Pictures showing installation of beams on a long structure (a bridge over Mureș river) in section 3.
09/02 (http://forum.peundemerg.ro/index.php?topic=165.msg127656#msg127656)  Pictures close to the border between sections 2 and 3.
09/03 (http://forum.peundemerg.ro/index.php?topic=165.msg127682#msg127682)  (as well as some previous posts) Discussions about proposals and plans for the connection between the motorway (Alba Iulia south exit) and Alba Iulia. It appears that no adequate solution is planned for the connection to and from the southern half of the city.
09/02 (http://forum.peundemerg.ro/index.php?topic=165.msg127724#msg127724)  (asp) Pictures showing further mobilisation and progress on sections 2 and 1...
09/04 (http://forum.peundemerg.ro/index.php?topic=165.msg127798#msg127798)  (asp) ...while section 4 is much more advanced.
09/04 (http://forum.peundemerg.ro/index.php?topic=165.msg127833#msg127833)  More construction pics from section 2...
09/05 (http://forum.peundemerg.ro/index.php?topic=165.msg127944#msg127944)  (asp) ... and also covering section 3 (two different sources).
09/07 (http://forum.peundemerg.ro/index.php?topic=165.msg128170#msg128170)  And more pics from section 4...
09/07 (http://forum.peundemerg.ro/index.php?topic=165.msg128195#msg128195)  ...followed again by section 3 (near the large structure at the Mureș river)...
09/09 (http://forum.peundemerg.ro/index.php?topic=165.msg128405#msg128405)  ...and yet again section 3.
09/10 (http://forum.peundemerg.ro/index.php?topic=165.msg128468#msg128468)  According to the official RNCMNR monthly report the following physical progress rates are quoted: Section 1: 12.80%, Section 2: 11.32%, Section 3: 53.50% and Section 4: 54.10%.
09/11 (http://forum.peundemerg.ro/index.php?topic=165.msg128541#msg128541)  Another set of pictures from section 3, followed in subsequent posts by an avalanche of pics from section 2.
09/21 (http://forum.peundemerg.ro/index.php?topic=165.msg129516#msg129516)  Nighttime video showing beam installation on structure at the A3-A10 interchange.
09/21 (http://forum.peundemerg.ro/index.php?topic=165.msg129595#msg129595)  (asp) More pictures from sections 3, 4 and 1.
09/25 (http://forum.peundemerg.ro/index.php?topic=165.msg129918#msg129918)  Aerial video of the entire section 3.
09/25 (http://forum.peundemerg.ro/index.php?topic=165.msg129918#msg129918)  Aerial video of the works at the A3 - A10 interchange.
09/28 (http://forum.peundemerg.ro/index.php?topic=165.msg130360#msg130360)  Pictures from section 3.
09/29 (http://forum.peundemerg.ro/index.php?topic=165.msg130554#msg130554)  (asp) More pics from all four sections of the motorway.
09/30 (http://forum.peundemerg.ro/index.php?topic=165.msg130776#msg130776)  Aerial video of the entire motorway construction site.
09/30 (http://forum.peundemerg.ro/index.php?topic=165.msg130782#msg130782)  Works at major structures on the motorway near Aiud.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on October 01, 2016, 01:45:18 AM
September 2016 * National roads

09/04 (http://forum.peundemerg.ro/index.php?topic=12.msg127772#msg127772)  Dashcam video of the Pocola - Beiuș section of DN 76 under rehabilitation...
09/04 (http://forum.peundemerg.ro/index.php?topic=12.msg127786#msg127786)  ...followed by construction pictures from the Beiuș - Ștei section of the same road.
09/09 (http://forum.peundemerg.ro/index.php?topic=12.msg128418#msg128418)  Works for the rehabilitation of DN 18 Moisei - Iacobeni (former contract 6R16 from Roads VI) have finally restarted, as can be seen in pictures.
09/13 (http://forum.peundemerg.ro/index.php?topic=12.msg128664#msg128664)  Another set of pics showing heavy works on DN 76 between Ștei and Oradea.
09/19 (http://forum.peundemerg.ro/index.php?topic=12.msg129295#msg129295)  Ingenious proposal regarding alignment optimisation of the planned widening of DN 7 and DN 71 past their intersection.
09/24 (http://forum.peundemerg.ro/index.php?topic=12.msg129856#msg129856)  Pictures showing resurfacing of DN 6 between Bucharest and Alexandria, that has been modernised part of the Roads II programme between 1998 and 2000.
09/29 (http://forum.peundemerg.ro/index.php?topic=12.msg130466#msg130466)  Long photo report from the long-due modernisation of the four-lane road DN 5 between Bucharest and Adunații Copăceni.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on October 01, 2016, 01:45:36 AM
September 2016 * Bypasses

09/08 (http://forum.peundemerg.ro/index.php?topic=7.msg128310#msg128310)  Pics showing progress on the Târgu Mureș bypass, near its future intersection with DN 15.
09/10 (http://forum.peundemerg.ro/index.php?topic=7.msg128450#msg128450)  Progress recorded for the construction of road bypasses during the last month, as per the official monthly report from the RNCMNR (ordered by progress achieved):
09/15 (http://forum.peundemerg.ro/index.php?topic=7.msg128881#msg128881)  RNCMNR informs about decision to use in-house resources (similar to the reconstruction of a subsection of the Orăștie - Sibiu section 3 motorway) to finalise works for the construction of the Suceava bypass.
09/17 (http://forum.peundemerg.ro/index.php?topic=7.msg129130#msg129130)  Photo report from the construction site of the Târgu Mureș bypass road.
09/23 (http://forum.peundemerg.ro/index.php?topic=7.msg129783#msg129783)  Responding to mounting local pressure regarding the construction of the Timișoara bypass (albeit only the eastern / southern section between DN 6 east and DN 59 south), the RNCMNR replies that their estimate for the launch date for the construction tender is T2/2017. However the FS still needs to be updated.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on November 03, 2016, 05:36:59 PM
October 2016 * Motorways: plans and projects

10/02 (http://forum.peundemerg.ro/index.php?topic=9.msg130960#msg130960)  Forum member argues that land acquisition should be completed as soon as possible for all GTMP motorway and expressway projects near urban areas, such as to avoid construction of buildings taking place on or along the right of way; sections proposed shown on map.
10/21 (http://forum.peundemerg.ro/index.php?topic=9.msg133780#msg133780)  General director of the NCARI states that tenders for remaining FS and / or designs of all motorway and expressway projects planned for the 2014 - 2020 programming period (according to the GTMP) will be started before the end of this year. These projects are Ploiești - Pașcani, Craiova - Pitești, Comarnic - Brașov, Făgăraș - Brașov and Iași - Ungheni.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on November 03, 2016, 05:39:11 PM
October 2016 * A1 Bucharest - Nădlac

10/01 (http://forum.peundemerg.ro/index.php?topic=2.msg130897#msg130897)  Construction pics from Lugoj - Deva motorway section 3: significant progress around the future Ilia interchange...
10/01 (http://forum.peundemerg.ro/index.php?topic=2.msg130932#msg130932)  ...and a set from a different source to support the claim.
10/01 (http://forum.peundemerg.ro/index.php?topic=2.msg130936#msg130936)  Works also advance on section 2 (pics). Forum member reports that it is "technically" possible to open subsection Dumbrava - Margina to traffic this year, let's hope that also "bureaucratically" it will be possible.
10/04 (http://forum.peundemerg.ro/index.php?topic=2.msg131267#msg131267)  Pictures showing finishing works on the same section.
10/05 (http://forum.peundemerg.ro/index.php?topic=2.msg131331#msg131331)  Long set of pics (stretching over several pages) from sections 3 and 4.
10/10 (http://forum.peundemerg.ro/index.php?topic=2.msg132315#msg132315)  The 22 km motorway between Cunța and Săliște (section 3 of the Orăștie - Sibiu motorway) reopens to traffic (initial opening: November 2014; closed to traffic: September 2015). 200 m of the motorway were completely reconstructed (km 60+545 to km 60+770); the process was managed in-house by NCARI (former RNCMNR), with some of the materials and equipment being supplied by private contractors.
10/11 (http://forum.peundemerg.ro/index.php?topic=2.msg132344#msg132344)  According to a forum member, the quality of the motorway surface is not the best - based on the quality of the ride. This does not refer to the 200 m reconstructed sector, but to the entire motorway, the cause being the initial construction quality.
10/11 (http://forum.peundemerg.ro/index.php?topic=2.msg132379#msg132379)  More pictures showing the Lugoj - Deva motorway section 2 nearing completion.
10/12 (http://forum.peundemerg.ro/index.php?topic=2.msg132435#msg132435)  Aerial pictures with labels showing explanations regarding the Holdea and Grind future interchanges on Lugoj - Deva motorway section 3.
10/12 (http://forum.peundemerg.ro/index.php?topic=2.msg132553#msg132553)  Aerial video of Lugoj - Deva motorway section 2...
10/13 (http://forum.peundemerg.ro/index.php?topic=2.msg132734#msg132734)  ... and progress achieved between August 29 and October 12 shown by comparing corresponding stills from videos.
10/14 (http://forum.peundemerg.ro/index.php?topic=2.msg132845#msg132845)  According to calendar presented by forum member, the revised environmental permit for the Lugoj - Deva motorway should be issued by November 15. This will allow restarting of works on section 4.
10/17 (http://forum.peundemerg.ro/index.php?topic=2.msg133204#msg133204)  NCARI's official monthly report lists the following progress rates for the construction of the Lugoj - Deva motorway: section 2: 46.96% (September) to 51.86% (October); section 3: 63.24% to 67.12%; section 4: 47.98% to 48.13%.
10/18 (http://forum.peundemerg.ro/index.php?topic=2.msg133353#msg133353)  Pics showing asphalt and finishing works on section 2.
10/19 (http://forum.peundemerg.ro/index.php?topic=2.msg133465#msg133465)  Local authorities push for the construction of another interchange on the A1 motorway, between the Șoimuș and Simeria interchanges, to better serve the Deva municipality.
10/21 (http://forum.peundemerg.ro/index.php?topic=2.msg133799#msg133799)  In an open letter addressed to the General Director of the NCARI, PIA expresses concerns regarding the following issues related to the A1 motorway:
10/24 (http://forum.peundemerg.ro/index.php?topic=2.msg134253#msg134253)  Generous set of pictures from Lugoj - Deva sections 4 and 3 construction site...
10/24 (http://forum.peundemerg.ro/index.php?topic=2.msg134367#msg134367)  ...followed by five short dashcam videos.
10/25 (http://forum.peundemerg.ro/index.php?topic=2.msg134508#msg134508)  NCARI publishes a PPT presentation showing the calendar and history of the reconstruction of Orăștie - Sibiu motorway section 3 (km 60+545 to km 60+770).
10/29 (http://forum.peundemerg.ro/index.php?topic=2.msg135282#msg135282)  Picture set from Lugoj - Deva motorway section 2, showing heavy works especially at and around the Margina interchange...
10/29 (http://forum.peundemerg.ro/index.php?topic=2.msg135331#msg135331)  ...more pics from the same location...
10/31 (http://forum.peundemerg.ro/index.php?topic=2.msg135637#msg135637)  ...as well as aerial pics explained with text labels.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on November 03, 2016, 05:39:33 PM
October 2016 * A3 Bucharest - Borș

10/03 (http://forum.peundemerg.ro/index.php?topic=6.msg131144#msg131144)  Aerial video of the Târgu Mureș (Ungheni) - Câmpia Turzii construction site. The environmental and construction permits have not been issued for over 75% of the section (despite one year having passed since signing the construction contracts), thus contractors cannot yet start complex works.
10/03 (http://forum.peundemerg.ro/index.php?topic=6.msg131171#msg131171)  Forum member documents the various locations in the movie above, section by section.
10/03 (http://forum.peundemerg.ro/index.php?topic=6.msg131237#msg131237)  Finishing works on the Gilău - Nădășel section, which unfortunately won't be usable for quite a while.
10/04 (http://forum.peundemerg.ro/index.php?topic=6.msg131289#msg131289)  Picture set documenting earthworks on the Popasului st. - Bucharest bypass section.
10/06 (http://forum.peundemerg.ro/index.php?topic=6.msg131560#msg131560)  The FS for the A3 connector to Oradea (a 20 km four-lane expressway) has been prepared by the Oradea Metropolitan Zone IDA, and was handed over today to the RNCMNR/NCARI.
10/06 (http://forum.peundemerg.ro/index.php?topic=6.msg131635#msg131635)  Notice to commence the design&build contract was issued to the contractor Impresa Construzioni Giuseppe Maltauro SpA - S.C. Viaponte ROM S.R.L. for the 16.8 km motorway Nădășel - Mihăiești. Contract was signed on May 26 this year and is to have a duration of 18 months (6 months design + 12 months construction). As such, the contract should be completed by April 7, 2018.
07/10 (http://forum.peundemerg.ro/index.php?topic=6.msg131748#msg131748)  Discussion about the opportunity of constructing, in the medium term, the Târgu Mureș - Brașov section. The GTMP does not include this project, however the Romanian Strategy for Territorial Development up to 2035 lists the entire A3 project (along with A1 and Sibiu - Brașov motorways) as a priority for "efficient economic development".
10/08 (http://forum.peundemerg.ro/index.php?topic=6.msg131798#msg131798)  User reports that essentially no works are to be seen on the Suplacu de Barcău - Borș section.
10/17 (http://forum.peundemerg.ro/index.php?topic=6.msg133216#msg133216)  According to the NCARI's official monthly progress report, the following physical completion rates are recorded for sections currently under construction: Târgu Mureș - Ogra section 2: 10.31% (up from 3.24% last month); Gilău - Nădășel: 82.4% (up from 82%); km 0 - 3+325 Bucharest: 6% (up from ~0%). No progress reported for the Suplacu de Barcău - Borș section.
10/21 (http://forum.peundemerg.ro/index.php?topic=6.msg133760#msg133760)  Launch of (re)tendering process for the construction contract of the Târgu Mureș - Ungheni motorway. This will be a Red FIDIC contract with construction estimated to take 18 months. Offers to be submitted by December 7, 2016.
10/21 (http://forum.peundemerg.ro/index.php?topic=6.msg133930#msg133930)  Launch of tendering process for the completion of the Gilău Someș river viaduct that will connect the motorway sections Câmpia Turzii - Gilău (open to traffic since 2009) and Gilău - Nădășel (currently 82.4% complete). Offers to be submitted by December 5, 2016. However, remaining finishing works on the Câmpia Turzii - Gilău motorway section still need to be retendered.
10/21 (http://forum.peundemerg.ro/index.php?topic=6.msg133933#msg133933)  Aerial video of the Suplacu de Barcău - Borș section (up to km 44). Construction works are virtually at a standstill, but no construction permit has been issued so far.
10/23 (http://forum.peundemerg.ro/index.php?topic=6.msg134130#msg134130)  Pictures showing construction progress on Târgu Mureș - Ogra motorway section 2.
10/24 (http://forum.peundemerg.ro/index.php?topic=6.msg134257#msg134257)  The Tureni local council formally rejected the design proposal for the A3 Mărtinești connector, which would significantly improve access from A3 to Cluj-Napoca, Romania's second largest city.
10/27 (http://forum.peundemerg.ro/index.php?topic=6.msg134892#msg134892)  Press article presents an overview of the progress regarding the Ogra - Câmpia Turzii motorway: archaeological diagnosis is completed (however clearance is not). Design is approved for section 1, with approval pending for section 2, and design still to be submitted for section 3.
10/28 (http://forum.peundemerg.ro/index.php?topic=6.msg135106#msg135106)  The tender for revising the feasibility study for 47 km of the Comarnic - Brașov motorway (i.e. excepting the end sections near Comarnic and Codlea) was started in July 2015, however it is still not clear whether the contract will be signed or the tender will be cancelled, following a long legal battle between the NCARI and the design company that won the tender. Should the tender be cancelled, the NCARI intends to launch a new tender which this time is to include also the detailed design.
10/28 (http://forum.peundemerg.ro/index.php?topic=6.msg135131#msg135131)  Two pictures taken in the same location on October 27 and 28 show the fast pace of construction on the Ungheni - Ogra motorway section.
10/28 (http://forum.peundemerg.ro/index.php?topic=6.msg135148#msg135148)  Aerial video of the Gilău - Nădășel motorway nearing completion.
10/31 (http://forum.peundemerg.ro/index.php?topic=6.msg135503#msg135503)  General director of the NCARI states that the 47 km of motorway between Ungheni (Târgu Mureș airport interchange) and Câmpia Turzii will open to traffic next year, however forum members doubt that this is feasible given the complexity of some structures to be built on this section.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on November 03, 2016, 05:39:47 PM
October 2016 * A7 Ploiești - Bacău - Siret

10/02 (http://forum.peundemerg.ro/index.php?topic=58.msg130997#msg130997)  (asp) Pictures show anemic construction progress on the Bacău bypass site.
10/29 (http://forum.peundemerg.ro/index.php?topic=58.msg135319#msg135319)  Pics and reports documenting errection of the construction camp and archaeological clearance for the Bacău bypass.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on November 03, 2016, 05:40:03 PM
October 2016 * A10 Sebeș - Turda

10/03 (http://forum.peundemerg.ro/index.php?topic=165.msg131125#msg131125)  Side-by-side stills (taken from aerial videos) showing progress between August 9 and September 30 for all four sections of the motorway.
10/04 (http://forum.peundemerg.ro/index.php?topic=165.msg131196#msg131196)  Pictures showing progress on section 4...
10/04 (http://forum.peundemerg.ro/index.php?topic=165.msg131264#msg131264)  ...and on section 3...
10/06 (http://forum.peundemerg.ro/index.php?topic=165.msg131555#msg131555)  ...as well as section 2.
10/12 (http://forum.peundemerg.ro/index.php?topic=165.msg132491#msg132491)  Description of progress on all three sections - hampered by the rainy season.
10/12 (http://forum.peundemerg.ro/index.php?topic=165.msg132575#msg132575)  Construction pictures from section 1.
10/14 (http://forum.peundemerg.ro/index.php?topic=165.msg132820#msg132820)  The two bridges over the Mureș river on section 2 (most likely both structures are on the critical path) see very limited progress, as documented by pictures.
10/14 (http://forum.peundemerg.ro/index.php?topic=165.msg132822#msg132822)  More pictures from sections 2 and 1. Forum member concludes that 2018 is a realistic estimate for finalising section 2, however not so likely for section 1.
10/14 (http://forum.peundemerg.ro/index.php?topic=165.msg132860#msg132860)  More pictures from sections 2 and 3.
10/15 (http://forum.peundemerg.ro/index.php?topic=165.msg132959#msg132959)  Photoreport from section 1 - includes ample explanation of pictures and of the construction progress.
10/17 (http://forum.peundemerg.ro/index.php?topic=165.msg133200#msg133200)  NCARI's monthly progress report shows satisfactory progress, with sections tagging along in pairs: sections 3 (59.5% / +6% compared to last month) and 4 (58.2% / +4.1%) one one hand, and sections 1 (15% / +2.2%) and 2 (11.46% / +0.14%) on the other hand.
10/23 (http://forum.peundemerg.ro/index.php?topic=165.msg134131#msg134131)  Pictures: construction update from sections 3 and 4...
10/24 (http://forum.peundemerg.ro/index.php?topic=165.msg134175#msg134175)  ... and 1...
10/24 (http://forum.peundemerg.ro/index.php?topic=165.msg134408#msg134408)  ... with another set (includes detailed explanations) from the same section.
10/25 (http://forum.peundemerg.ro/index.php?topic=165.msg134526#msg134526)  Pictures: beam placement (over the railway line) on the major structure at the Aiud interchange...
10/26 (http://forum.peundemerg.ro/index.php?topic=165.msg134802#msg134802)  ...with more pics and a movie here.
10/28 (http://forum.peundemerg.ro/index.php?topic=165.msg135218#msg135218)  Drone video of section 4. Construction progress is hampered by power towers on the alignment (multiple locations) still awaiting relocation.
10/31 (http://forum.peundemerg.ro/index.php?topic=165.msg135620#msg135620)  Pictures from section 4...
10/31 (http://forum.peundemerg.ro/index.php?topic=165.msg135622#msg135622)  ...and section 2...
10/31 (http://forum.peundemerg.ro/index.php?topic=165.msg135733#msg135733)  ...and also section 1.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on November 03, 2016, 05:40:22 PM
October 2016 * National roads

10/01 (http://forum.peundemerg.ro/index.php?topic=12.msg130944#msg130944)  Construction update from the DN 18 Moisei - Iacobeni road modernisation project, section 1 Moisei - Borșa.
10/10 (http://forum.peundemerg.ro/index.php?topic=12.msg132237#msg132237)  More pictures from national road rehabilitation in northern Romania: DN 17D, DN 17C and DN 18.
10/11 (http://forum.peundemerg.ro/index.php?topic=12.msg132414#msg132414)  Dashcam video of DN 1R from Huedin to Albac (formerly DJ 108) crossing the Apuseni National Park - finally paved with asphalt from one end to the other.
10/16 (http://forum.peundemerg.ro/index.php?topic=12.msg133097#msg133097)  Pictures showing modernisation of DN 5 south of Bucharest.
10/19 (http://forum.peundemerg.ro/index.php?topic=12.msg133498#msg133498)  Construction pictures from section 2 (Borșa - Șesuri) of DN 18 Moisei - Iacobeni... however part of this section appears to be in a different season.
10/23 (http://forum.peundemerg.ro/index.php?topic=12.msg134243#msg134243)  DN 18 from Baia Mare to Sighetu Marmației (contractor: Aktor) is still under modernisation, ready to enter the 6th construction year.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on November 03, 2016, 05:40:46 PM
October 2016 * Bypasses

10/01 (http://forum.peundemerg.ro/index.php?topic=7.msg130929#msg130929)  Brașov bypass section 1 (DN 1 - DN 11) appears to be almost ready for opening, as shown in these pictures. Forum member ranks the quality of the wearing course as mediocre.
10/04 (http://forum.peundemerg.ro/index.php?topic=7.msg131205#msg131205)  Signature of the contract for the supervision of works for the construction of the Satu Mare bypass.
10/04 (http://forum.peundemerg.ro/index.php?topic=7.msg131324#msg131324)  Pictures showing construction of the Târgu Jiu bypass. Some progress at structures, but very limited earthworks progress.
10/06 (http://forum.peundemerg.ro/index.php?topic=7.msg131562#msg131562)  The FS for the A3 connector to Oradea has been prepared by the Oradea Metropolitan Zone IDA, and was handed over today to the NCARI, which will supposedly implement the construction. This will be a 20 km four-lane expressway with median barrier, however not entirely grade-separated, as it will include two roundabouts.
10/09 (http://forum.peundemerg.ro/index.php?topic=7.msg131928#msg131928)  Pictures from the Oradea bypass, with the Nojoridului and Ciheiului grade separation projects nearing completion.
10/13 (http://forum.peundemerg.ro/index.php?topic=7.msg132646#msg132646)  Pictures: the opening to traffic of the Brașov bypass (section DN 1 south - DN 11) depends on the completion of the interchange between the bypass and DN 11.
10/17 (http://forum.peundemerg.ro/index.php?topic=7.msg133220#msg133220)  According to the NCARI monthly report, the construction of the Târgu Mureș bypass has advanced during the last month from 18.72% to 22.16%...
10/19 (http://forum.peundemerg.ro/index.php?topic=7.msg133536#msg133536)  ...and pictures to document progress.
10/19 (http://forum.peundemerg.ro/index.php?topic=7.msg133606#msg133606)  Progress for the construction of road bypasses during the last month, as per the official NCARI monthly report:
10/20 (http://forum.peundemerg.ro/index.php?topic=7.msg133675#msg133675) NCARI informs that the contract for the construction of the Beiuș - Ștei bypass has been signed on October 5th. The contract value is 257.4 MRON (approximately 58 MEUR) and construction is expected to take 24 months following the issuing of the notice to commence.
This project is in fact an extended relocation of DN 76 (the new road will have 27.2 km), from north of Beiuș to south of Ștei, intercepting DJ 764F to Salonta, DJ 763 to Padiș hiking area in the Apuseni National Park and DN 75 to Arieșeni, Câmpeni and Turda, and bypassing multiple settlements (Beiuș, Drăgănești, Sudrigiu, Rieni, Petrileni, Ștei and Lunca). This will be a 2x1 road almost entirely grade-separated...
10/23 (http://forum.peundemerg.ro/index.php?topic=7.msg134247#msg134247)  ...and a map showing its alignment can be seen here.
10/26 (http://forum.peundemerg.ro/index.php?topic=7.msg134716#msg134716)  The Nojoridului overpass has been open to traffic, bringing the Oradea bypass one step closer to being a fully grade-separated expressway.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on December 21, 2016, 03:23:06 AM
November 2016 * Motorways: plans and projects

11/05 (http://forum.peundemerg.ro/index.php?topic=9.msg136442#msg136442)  Forum member makes a realistic forecast regarding motorways expected to open in 2017: A1 Lugoj - Deva section 2 (Holdea - Ilia), A3 Bucharest entrance (3 km) and A10 Sections 3 and 4 (Aiud - Turda). Thus, it appears that not only 2016 (15 km expected) but also 2017 will be dire in terms of motorway openings.
11/08 (http://forum.peundemerg.ro/index.php?topic=9.msg136875#msg136875)  Zoomable OSM-based map (http://proinfrastructura.ro/proiecteinfrastructura.html#map=10/46.561/24.074/0) showing past/expected motorway openings is also updated accordingly (blue = expected opening; red = expected finishing of construction but without traffic access).
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on December 21, 2016, 03:24:47 AM
credits to user TibiV for preparing the Romanian version of this month's A1 digest

November 2016 * A1 Bucharest - Nădlac

11/02 (http://forum.peundemerg.ro/index.php?topic=2.msg135854#msg135854)  Photoreport from Lugoj - Deva motorway covering the Ilia interchange from section 3 as well as the ecoducts from section 4 (http://forum.peundemerg.ro/index.php?topic=2.msg135867#msg135867).
11/02 (http://forum.peundemerg.ro/index.php?topic=2.msg135914#msg135914)  Detailed report from the Aciliu viaduct from the Orăștie - Sibiu motorway: existing problems, remedial works executed so far and earth slides from the cut from the southern end of the viaduct (https://www.google.ro/maps/@45.8269655,23.868571,3064m/data=!3m1!1e3).
11/03 (http://forum.peundemerg.ro/index.php?topic=2.msg136095#msg136095)  Aerial videos covering sections 2, 3 and 4 of the Lugoj - Deva motorway. Important progress can be seen at some construction sites, however also high voltage power towers that still need to be relocated.
11/14 (http://forum.peundemerg.ro/index.php?topic=2.msg137743#msg137743)  Pictures from the Margina interchange (http://www.openstreetmap.org/#map=13/45.8660/22.2605), showing intense works and significant progress. This is the access interchange for the 15 km section Dumbrava - Margina, part of section 2 of the Lugoj - Deva motorway, which will most likely open to traffic before Christmas.
11/14 (http://forum.peundemerg.ro/index.php?topic=2.msg137753#msg137753)  Winter pictures from the Lugoj - Deva motorway section 3 construction site. Many sectors are finalised, including the wearing course and guardrails, and remedial works can be seen in other sectors addressing issues mainly regarding water drainage.
11/15 (http://forum.peundemerg.ro/index.php?topic=2.msg137927#msg137927)  Design sketches of the future "temporary" Holdea interchange (http://www.openstreetmap.org/#map=14/45.8885/22.4218), the western access point for the Lugoj - Deva motorway section 3. The section between Holdea and Margina (see above) will most likely be the only segment of A1 between Nădlac (at the western border) and Sibiu for which works will be delayed for some years, since it requires the construction of some motorway tunnels (and the tender for construction is yet to be launched). Between Margina and Holdea traffic will use approximately 15 km of the national road DN 68A (http://www.openstreetmap.org/#map=13/45.8686/22.3759), a winding two-lane road.
11/16 (http://forum.peundemerg.ro/index.php?topic=2.msg138203#msg138203)  Chart showing the montly progress for the three motorway sections under construction between Dumbrava and Deva.
11/20 (http://forum.peundemerg.ro/index.php?topic=2.msg138785#msg138785)  A comprehensive set of pics from sections 4 and 3 of the Lugoj - Deva motorway, from the Brănișca ecoduct towards the Ilia interchange, then covering the Mureș bridge and finally the Grind interchange.
11/22 (http://forum.peundemerg.ro/index.php?topic=2.msg139111#msg139111)  The Ministry of Transport and NCARI have presented the final alignment for the future Sibiu - Pitești motorway. Its length will be 123.037 km and it will have 10 interchanges. The total length of tunnels will be around 13 km (i.e. 7 tunnels with a total length of 6430 m for each carriageway). The alignment can be seen on OSM support here (http://hotnews.maps.arcgis.com/apps/Embed/index.html?webmap=3e3ec18e5a7f47ef8db5c4d14f3d4aad&extent=23.6025,44.9734,25.6309,45.7339&zoom=true&scale=true&legend=true&disable_scroll=false&theme=light).
11/24 (http://forum.peundemerg.ro/index.php?topic=2.msg139672#msg139672)  According to forum member, the revised environmental permit for the Lugoj - Deva motorway will be issued by mid December.
11/26 (http://forum.peundemerg.ro/index.php?topic=2.msg139996#msg139996)  Ample photoreport covering all three sections under construction of the Lugoj - Deva motorway...
11/28  ...as well as corresponding drone videos covering section 4 (http://forum.peundemerg.ro/index.php?topic=2.msg140231#msg140231) and section 3 (http://forum.peundemerg.ro/index.php?topic=2.msg140421#msg140421).
11/29 (http://forum.peundemerg.ro/index.php?topic=2.msg140517#msg140517)  Aerial video of the Dumbrava - Margina motorway, hopefully to open for traffic before Christmas.
11/30 (http://forum.peundemerg.ro/index.php?topic=2.msg140670#msg140670)  Deep bores for geotechnical investigations on section 4 of the future Sibiu - Pitești motorway.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on December 21, 2016, 03:25:35 AM
November 2016 * A3 Bucharest - Borș

11/01 (http://forum.peundemerg.ro/index.php?topic=6.msg135772#msg135772)  Aerial video of the construction works of the southernmost section of A3: access to northern Bucharest (http://www.openstreetmap.org/#map=14/44.4969/26.1525); expected opening date of the section between Popasului street and the Bucharest bypass is December 2016.
11/03 (http://forum.peundemerg.ro/index.php?topic=6.msg136134#msg136134)  Photo report from Strabag's A3 section near Târgu Mureș (Ungheni - Ogra), see red section on map linked at end of paragraph. This is the most advanced (and with the highest construction dynamics) section of the Câmpia Turzii - Târgu Mureș motorway, however section won't be usable unless interchange on adjacent western lot will be also completed in time (see map (http://proinfrastructura.ro/proiecteinfrastructura.html#map=13/46.45/24.38/0)).
11/04 (http://forum.peundemerg.ro/index.php?topic=6.msg136265#msg136265)  (asp) Notice of termination of contract for the construction of the Suplacu de Barcău - Borș A3 motorway section. Initially the contractors (Corsan Corviam Construction S.A. – S.C. Selina S.R.L. – Louis Berger Sas – S.C. Road Consulting & Design Solutions S.R.L. and S.C. RCM Construzioni SRL, leader of the association RCM Construzioni SRL / Imob Lux Construct SRL / Consinit SRL / Societatea de Construcţii Napoca SA / Impresa Ferrara S.N.C Di Angela & Rossella Ferrara / SC T Dancor RomConstruct SRL / SC Shelter Construct SRL / Associazione Cooperativa Muratori & Affini Ravenna S.C.P.A. / Schiavo & C.SpA /Eurocerad International SRL) submitted the notice, however the client (NCARI) rejected the notice and submitted its own. This in fact means that realistically construction will most likely restart in 2018, with the entire section possibly finalised by 2020...
11/05 (http://forum.peundemerg.ro/index.php?topic=6.msg136380#msg136380)  ...but according to a press article the General Director of the NCARI states that the construction will be retendered "before the end of this year".
11/16 (http://forum.peundemerg.ro/index.php?topic=6.msg138202#msg138202)  Graph showing progress rates during the last month for some of the A3 sections under construction (based on data from the official NCARI monthly report).
11/20 (http://forum.peundemerg.ro/index.php?topic=6.msg138777#msg138777)  Forum member points out that 13 months have passed since the initial deadline for the finalisation of the feasibility study for the ~2.4 km Meseș Tunnel (part of the A3 near Zalău). No communication from NCARI regarding this contract.
11/21 (http://forum.peundemerg.ro/index.php?topic=6.msg138967#msg138967)  Construction pics from the Popasului interchange on A3/Bucharest, at the southern end of the section planned to open to traffic in December.
11/30 (http://forum.peundemerg.ro/index.php?topic=6.msg140659#msg140659)  More construction pics from the Ungheni - Ogra section (progress stands at 11.4% as per the NCARI November report).
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on December 21, 2016, 03:25:52 AM
October 2016 * A7 Ploiești - Bacău - Siret

11/04 (http://forum.peundemerg.ro/index.php?topic=58.msg136353#msg136353)  Earthworks pictures, no work on structures reported...
11/18 (http://forum.peundemerg.ro/index.php?topic=58.msg138469#msg138469)  ...and pictures to contradict the last part of the statement above :)
11/24 (http://forum.peundemerg.ro/index.php?topic=58.msg139462#msg139462)  The much-anticipated tender for the feasibility study (including detailed design) for the "high speed road" [A/DX]7 (consultant to recommend and NCARI to decide if motorway or expressway) has been launched for four sections between Ploiești and Pașcani (segmented at Buzău, Focșani and Bacău). Contracts are expected to have a duration of 24 months (14 for the feasibility study, 6 for the detailed design and 4 for the preparation of the tender documents for construction). Deadline for the submission: January 5 / 9, 2017.
11/26 (http://forum.peundemerg.ro/index.php?topic=58.msg139908#msg139908)  Pictures showing structure work on the Bacău bypass.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on December 21, 2016, 03:26:10 AM
November 2016 * A10 Sebeș - Turda

11/02 (http://forum.peundemerg.ro/index.php?topic=165.msg135882#msg135882)  Forum member reports construction is ongoing at a satisfactory pace on sections 3 and 4 despite cold weather (2-3 oC above zero).
11/02 (http://forum.peundemerg.ro/index.php?topic=165.msg135936#msg135936)  Pictures showing ABC and AWC works on section 4.
11/04 (http://forum.peundemerg.ro/index.php?topic=165.msg136224#msg136224)  Forum member reports that significant works (both earthworks and structures) are ongoing on section 2 too...
11/05 (http://forum.peundemerg.ro/index.php?topic=165.msg136412#msg136412)  ...and pictures from the same section.
11/05 (http://forum.peundemerg.ro/index.php?topic=165.msg136505#msg136505)  Long photoreport from sections 2 and 1. These two sections are finally catching up (in terms of progress rate) with sections 3 and 4. At this moment the motorway construction sites from the future Sebeș - Turda motorway are the most dynamic in Romania.
11/06 (http://forum.peundemerg.ro/index.php?topic=165.msg136626#msg136626)  More pics from section 3 (first post) and 2 (second post).
11/08 (http://forum.peundemerg.ro/index.php?topic=165.msg136947#msg136947)  The construction permit for the Sebeș A1xA10 interchange (part of section 1) is still not issued, forum member predicts it will be out soon...
11/09 (http://forum.peundemerg.ro/index.php?topic=165.msg137113#msg137113)  ...and another member lists the most challenging points on section 1, most of which are structures where work has not yet started.
11/17 (http://forum.peundemerg.ro/index.php?topic=165.msg138312#msg138312)  Graph showing progress rates during the last month for the four A10 sections (based on data from the official NCARI monthly report).
11/19 (http://forum.peundemerg.ro/index.php?topic=165.msg138625#msg138625)  Generous set of construction pics from section 3...
11/21 (http://forum.peundemerg.ro/index.php?topic=165.msg138935#msg138935)  ...and 2, courtesy of the same member.
11/25 (http://forum.peundemerg.ro/index.php?topic=165.msg139849#msg139849)  (asp) Ample set of pictures covering sections 4, 3 and 2.
11/30 (http://forum.peundemerg.ro/index.php?topic=165.msg140645#msg140645)  And a different take: a "nature and the motorway" set of pics, followed by other construction pics from section 3.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on December 21, 2016, 03:26:29 AM
November 2016 * National roads

11/04 (http://forum.peundemerg.ro/index.php?topic=12.msg136301#msg136301)  DN 14A between Mediaș and Târnăveni has received a much needed resurfacing. However, the section between Târnăveni and Iernut still needs attention, part of which is surfaced with jointed concrete pavement in rather poor condition.
11/06 (http://forum.peundemerg.ro/index.php?topic=12.msg136642#msg136642)  Pictures from modernisation of the Oradea - Deva road (E79 / DN 76), much work still to be done.
11/20 (http://forum.peundemerg.ro/index.php?topic=12.msg138763#msg138763)  More pics from the reconstruction of DN 76.
11/25 (http://forum.peundemerg.ro/index.php?topic=12.msg139689#msg139689)  A long and heated debate pro/con reconfiguring the DN 2 / DN 28 corridor, currently a 1+1 road with wide (2.5 m) paved shoulders into a [2+1] road.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on December 21, 2016, 03:26:45 AM
November 2016 * Bypasses

11/02 (http://forum.peundemerg.ro/index.php?topic=7.msg135934#msg135934)  Aerial video of the Bucharest ringroad widening (from two to four lanes) between DN 7 and A1.
11/15 (http://forum.peundemerg.ro/index.php?topic=7.msg137981#msg137981)  An overview of the current status regarding the widening of the Bucharest ringroad (most of it still a two lane road), clockwise from north --- section DN 2 - A2: design almost complete, tender to be launched by December, estimated completion late 2017; A2 - DN 5: a decision to be made regarding the actual technical solution to be implemented by May 2017, design to follow afterwards; DN 5 - A1: tender for D&B contract to be launched by December, estimated completion by 2019; A1 - DN 7: completion expected this December.
11/18 (http://forum.peundemerg.ro/index.php?topic=7.msg138496#msg138496)  A new 7.3 km four-lane section of the eastern Brașov bypass, between DN 11 and DN 1, opened to traffic today.
11/18 (http://forum.peundemerg.ro/index.php?topic=7.msg138541#msg138541)  According to the NCARI monthly report the following progress was recorded this month for bypasses under construction or widening: from 84% to 91% for Brașov bypass widening between DN 13 and DN 11; from 10% to 15% for the Tecuci bypass; from 22.16% to 23.57% for the Târgu Mureș bypass; from 25% to 26.5% for the Târgu Jiu bypass; and from 0% to 0.04% for the Bacău bypass (first carriageway of future A7).
11/25 (http://forum.peundemerg.ro/index.php?topic=7.msg139864#msg139864)  According to press release, the notice to commence the construction of the Rădăuți bypass (a small town in the far northeast) was issued today; it is interesting to note that the signature of the construction contract took place in May 2011.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on January 09, 2017, 05:03:01 PM
December 2016 * Motorways: plans and projects

12/06 (http://forum.peundemerg.ro/index.php?topic=9.msg141356#msg141356)  A survey conducted by a professional company (sample size 1122) shows that Romanians strongly support actions aimed at developing road infrastructure (modernising existing roads and construction of motorways) over actions and programs aimed at modernising rail infrastructure and rolling stock.
12/06 (http://forum.peundemerg.ro/index.php?topic=9.msg141379#msg141379)  Analysis of a forum member (followed by some discussion) regarding the limited involvement and passive approach of most city authorities is solving issues pertaining to urban and periurban road infrastructure connectivity to the national networks.
12/08 (http://forum.peundemerg.ro/index.php?topic=9.msg141697#msg141697)  Forum member points out that, as of December 1, the total value of payments made in 2016 by NCARI [and RNCMNR] for motorway construction is roughly 158.9 million EUR (however significant payments are expected for December). According to press article (see post above (http://forum.peundemerg.ro/index.php?topic=9.msg141692#msg141692)), the 2016 budget allocation for construction of motorways was 384.4 million EUR.
12/16 (http://forum.peundemerg.ro/index.php?topic=9.msg142727#msg142727)  PIA vicepresident (and the founder of this forum) points out that no more than 50 km of motorways can be realistically expected to open to traffic in 2017, namely 28 km of A10 (from Aiud to Turda) and 22 km from A1 (section 3, from Ilia to Holdea (http://www.openstreetmap.org/#map=13/45.9085/22.5390)). In addition 19 km of motorway would be finalised in 2017 without being usable.
12/22 (http://forum.peundemerg.ro/index.php?topic=9.msg143224#msg143224)  Forum member posts official letter received from NCARI regarding the status of the future motorways in the corridor Bacău/Comarnic - Brașov - Făgăraș - Sibiu. The contract for the preparation of the feasibility study for the Făgăraș - Sibiu section (suspended since November 18, 2015) will see continuation of implementation starting with January 17, 2017. Tender documents are currently being prepared for contracting the revision of the FS for the Făgăraș - Brașov section. No preparation is expected to take place for the Brașov - Bacău section before 2021. The contract for the revision the feasibility study for sections Comarnic - Cristian is expected to be signed soon (consultant Consitrans SRL - 3TI Progetti Italy - Ingegneria Integrata SPA, contract value 9.6 million RON).
12/28 (http://forum.peundemerg.ro/index.php?topic=9.msg143739#msg143739)  Press article presents comparative analysis covering the last 5 years in terms of investments in public infrastructure. Investment spending in the first 11 months has decreased from 4% of GDP (2013) to 2.9% of GDP (2016). 2016 also stands out as the year with no new motorway sections open to traffic.
12/29 (http://forum.peundemerg.ro/index.php?topic=9.msg143783#msg143783)  PIA vicepresident points out that in addition to the two motorway sections currently finalised but not usable by traffic, there is a risk for this situation to appear for 3 other sections in 2017 (A3 Gilău - Nădășel, A3 Ungheni - Ogra and A1 Dobra - Holdea).
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on January 09, 2017, 05:17:49 PM
credits to user TibiV for preparing the Romanian version of this month's A1 digest

December 2016 * A1 Bucharest - Nădlac

12/05 (http://forum.peundemerg.ro/index.php?topic=2.msg141156#msg141156)  Short photoreport from the Margina interchange from section 2 of the Lugoj - Deva motorway. This is the access interchange for the 15 km Dumbrava - Margina motorway section that should have been open to traffic before the end of this month.
12/07 (http://forum.peundemerg.ro/index.php?topic=2.msg141554#msg141554)  Photos from the showing the poor shape of DN 73C, which will be the main connection between Râmnicu Vâlcea and the Tigveni interchange of the future Sibiu - Pitești motorway. Pics present two areas (separated by around 1 km) where land slides have been a problem for decades. A1 Sibiu - Pitești will have 5 sections, however the modernisation of DN 73C, including the construction of a new 1.5 km road segment, is included in the project as "section sx6".
12/09 (http://forum.peundemerg.ro/index.php?topic=2.msg141925#msg141925)  The revised environmental permit for the entire Lugoj - Deva motorway (km 0+000 – km 100+014) was issued today. The 98-page document (http://forum.peundemerg.ro/index.php?action=dlattach;topic=2.0;attach=715) comprises a lot of technical data about the motorway. It appears that the construction permit for the Margina interchange was also issued today.
12/10 (http://forum.peundemerg.ro/index.php?topic=2.msg142095#msg142095)  A comprehensive photoreport shows heavy ongoing works for finalising the Margina interchange on section 2 of the Lugoj - Deva motorway.
12/11 (http://forum.peundemerg.ro/index.php?topic=2.msg142122#msg142122)  Pics from section 4 of the same motorway. Half of this section (between Brănișca and Ilia) already has upper pavement layers and guardrails.
12/11 (http://forum.peundemerg.ro/index.php?topic=2.msg142147#msg142147)  Another set of pics from the Margina interchange, hopefully to be open by Christmas. The interchange layout can be seen here (http://i.imgur.com/iCDzXcv.png) or here (http://autostrada-lugoj-deva-lot2.ro/wp-content/uploads/2012/02/nod.jpg).
12/18 (http://forum.peundemerg.ro/index.php?topic=2.msg142894#msg142894)  Video recorded by the IPA team at the Margina interchange. Traffic should open in 3 to 5 days, apparently the only thing missing are horizontal markings on a few hundred meters.
12/21 (http://forum.peundemerg.ro/index.php?topic=2.msg143140#msg143140)  Heated debate about NCARI's disappointing decision (link to official statement (http://cnadnr.ro/ro/comunicare/comunicate-de-presa/interes-general/comunicat-de-pres%C4%83-lugoj-%E2%80%93-deva-21122016)) not to open to traffic the Traian Vuia / Dumbrava - Margina 15 km motorway section, despite works being completed, legal/bureaucratic reasons being invoked.
12/22 (http://forum.peundemerg.ro/index.php?topic=2.msg143270#msg143270)  The phrase "museum of the motorway A1 Dumbrava - Margina" is patented in IPA's photoreport proving that the motorway is fully completed; phrase is relayed by much of the Romanian mass-media.
12/23 (http://forum.peundemerg.ro/index.php?topic=2.msg143366#msg143366)  Pictures from section 3 of the Lugoj - Deva motorway, starting from the Ilia interchange, covering the bridge over the Mureș river and finally the Grind interchange.
12/24 (http://forum.peundemerg.ro/index.php?topic=2.msg143478#msg143478)  Christmas present from the IPA: drone aerial video of the Dumbrava - Margina motorway section, finalised but not open to traffic.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on January 09, 2017, 05:18:15 PM
December 2016 * A3 Bucharest - Borș

12/01 (http://forum.peundemerg.ro/index.php?topic=6.msg140813#msg140813)  Forum member reports that the constructor of the Gilău - Nădășel section is seen working despite today being the Romanian national day (reference is made to obeyance of the Christian as opposed to the non-religious public holidays)...
12/03 (http://forum.peundemerg.ro/index.php?topic=6.msg140964#msg140964)  ...however as of today all construction work has been suspended for the winter season.
12/04 (http://forum.peundemerg.ro/index.php?topic=6.msg141061#msg141061)  Construction pics from around the Popasului interchange on the southernmost section of A3 (inside the Bucharest urban area).
12/04 (http://forum.peundemerg.ro/index.php?topic=6.msg141084#msg141084)  "Preparing for hibernation": pictures from section Gilău - Nădășel.
12/04 (http://forum.peundemerg.ro/index.php?topic=6.msg141099#msg141099)  Drone video from the same section. Works remaining for 2017 are: laying the wearing course (for less than half of the section), horizontal signing as well as solving two land slides.
12/05 (http://forum.peundemerg.ro/index.php?topic=6.msg141258#msg141258)  Minister of transport states that he expects that the construction of the Suplacu de Barcău - Borș section (construction contract terminated last month) will be retendered in two sections, with tender expected to start "during his mandate" (implying that the tender would be launched this year).
12/08 (http://forum.peundemerg.ro/index.php?topic=6.msg141774#msg141774)  More pics from the A3 section in the Bucharest urban area that is expected to open to traffic this year...
12/20 (http://forum.peundemerg.ro/index.php?topic=6.msg143065#msg143065)  ...and an aerial video (credits to ASCORO (http://www.construim-romania.ro/)) of this six-lane urban motorway with no hard shoulders, ready to open to traffic...
12/21 (http://forum.peundemerg.ro/index.php?topic=6.msg143197#msg143197)  (asp) ...however according to inside information from various forum members, the motorway will not see traffic in 2016 (as it previously had been expected).
12/22 (http://forum.peundemerg.ro/index.php?topic=6.msg143335#msg143335)  Graph showing progress rates during the last month for some of the A3 sections under construction (based on data from the official NCARI monthly report).
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on January 09, 2017, 05:18:42 PM
December 2016 * A7 Ploiești - Bacău - Siret

12/05 (http://forum.peundemerg.ro/index.php?topic=58.msg141250#msg141250)  Maps showing proposed alignments (based on a 2003 - 2006 prefeasibility study) for the future Ploiești - Buzău - Bacău - Sculeni (RO/MD border) motorway (post text contains link to higher resolution images)...
12/06 (http://forum.peundemerg.ro/index.php?topic=58.msg141373#msg141373)  ...with forum members commenting on rather low number of proposed access points, suggesting additional interchanges especially near key towns along the route.
12/07 (http://forum.peundemerg.ro/index.php?topic=58.msg141599#msg141599)  IPA vicepresident shows concern about no clear instructions (in the tender documents) regarding the procedure for deciding between motorway and expressway during the preparation stage for the Ploiești - Pașcani corridor; he reminds that IPA has taken a public stance supporting the construction of a motorway (not expressway).
12/08 (http://forum.peundemerg.ro/index.php?topic=58.msg141732#msg141732)  Contractor of the Bacău bypass posts new pics showing piling...
12/12 (http://forum.peundemerg.ro/index.php?topic=58.msg142229#msg142229)  ...and other works.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on January 09, 2017, 05:19:02 PM
December 2016 * A10 Sebeș - Turda

12/04 (http://forum.peundemerg.ro/index.php?topic=165.msg141072#msg141072)  Construction pics of sections 3 and 4 taken while driving on the parallel national road.
12/11 (http://forum.peundemerg.ro/index.php?topic=165.msg142158#msg142158)  Propitious weather permits continuation of works (even paving) during December, as seen in these pictures.
12/16 (http://forum.peundemerg.ro/index.php?topic=165.msg142773#msg142773)  More December construction pics, this time from section 2.
12/21 (http://forum.peundemerg.ro/index.php?topic=165.msg143115#msg143115)  More photos from the same section, mostly piling-related.
12/22 (http://forum.peundemerg.ro/index.php?topic=165.msg143300#msg143300)  Aerial video from section 3...
12/22 (http://forum.peundemerg.ro/index.php?topic=165.msg143337#msg143337)  ...as it stands at a 66.5% completion rate, according to this month's official report.
12/23 (http://forum.peundemerg.ro/index.php?topic=165.msg143432#msg143432)  Photoreport from section 4 (current progress is 60.5%).
12/29 (http://forum.peundemerg.ro/index.php?topic=165.msg143845#msg143845)  This year's final set of pics covers the area around the limit between sections 2 and 3.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on January 09, 2017, 05:19:24 PM
December 2016 * National roads

12/04 (http://forum.peundemerg.ro/index.php?topic=12.msg140997#msg140997)  Anemic progress photodocumented regarding the modernisation of DN 5 south of Bucharest between the capital and Adunații Copăceni.
12/05 (http://forum.peundemerg.ro/index.php?topic=12.msg141167#msg141167)  Notice to commence issued for the modernisation of DN 18 between Cârlibaba and Iacobeni in the far north (part of the Roads VI modernisation programme); works could be completed by the end of 2017.
12/08 (http://forum.peundemerg.ro/index.php?topic=12.msg141773#msg141773)  Dashcam video showing completion of works for the modernisation of DN 76 between Brad and Ionești (http://www.openstreetmap.org/#map=12/46.2011/22.6720) (km 35+432 - km 55+425). This in fact is the only section completed so far of the ill-fated project regarding the modernisation of the ~180 km DN 76 / E79 between Deva and Oradea, a project started in 2002. Constructor for this contract (5R10b, in fact formerly terminated / works retendered in 2012) was PORR BAU GmbH.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on January 09, 2017, 05:19:44 PM
December 2016 * Bypasses

12/05 (http://forum.peundemerg.ro/index.php?topic=7.msg141190#msg141190)  A new 6.5 km two-lane road (labeled as DN 65F here (http://www.openstreetmap.org/#map=14/44.2878/23.9152)) functioning as the eastern bypass of Craiova (improperly called "the southern bypass"), that connects DN 6 eastbound (to Alexandria and Bucharest) with DN 65 (to Pitești and Sibiu, also alternate route to Bucharest via motorway A1) opened to traffic on December 6. It connects, via the northern bypass (opened in 2006) to DN 6 westbound, as well as to secondary national roads 6B and 65C. Contractor was S.E.C.O.L.- Societa Edile Construzioni e Lavori S.A. & SECOL Romania SRL & S.E.C.O.L. S.p.A.
12/05 (http://forum.peundemerg.ro/index.php?topic=7.msg141284#msg141284)  ...a link to a dashcam video is available in this post...
12/07 (http://forum.peundemerg.ro/index.php?topic=7.msg141625#msg141625)  ...as well as a drone video.
12/17 (http://forum.peundemerg.ro/index.php?topic=7.msg142847#msg142847)  Pictures from the construction of the Târgu Mureș bypass (currently at 24.3% physical progress).
12/19 (http://forum.peundemerg.ro/index.php?topic=7.msg142970#msg142970)  Aerial video of the newly-opened section of the Brașov bypass.
12/19 (http://forum.peundemerg.ro/index.php?topic=7.msg142983#msg142983)  Aerial video of the construction of the interchange between DJ 103 and the Brașov bypass - the northern section between DN 13 and DN 10, currently being widened to four lanes (progress is at 91%).
12/20 (http://forum.peundemerg.ro/index.php?topic=7.msg143080#msg143080)  According to the NCARI monthly report the following progress was recorded this month for bypasses under construction or widening (only progress greater than or equal to 1% is mentioned): from 91% to 92% for the Caracal bypass; from 2% to 3.6% for the Mihăilești (DN 6) bypass; from 55% to 57% for the Bucharest bypass widening between DN 7 and A1; from 26.5% to 28.5% for the Târgu Jiu bypass.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on February 11, 2017, 08:20:52 PM
January 2017 * Motorways: plans and projects

01/10 (http://forum.peundemerg.ro/index.php?topic=9.msg144941#msg144941)  Graphical representation of motorway construction payments in 2016. The lion's share went to contracts on two motorway axes: Lugoj - Deva and Sebeș - Turda - Târgu Mureș.
01/16 (http://forum.peundemerg.ro/index.php?topic=9.msg145574#msg145574)  According to press article, a 11.1% increase of road freight tonne-kilometers, the third largest in the EU (after BG and HR; EU average was 2.2%), was recorded in Romania between 2014 and 2015.

January 2017 * A1 Bucharest - Nădlac

01/12 (http://forum.peundemerg.ro/index.php?topic=2.msg145261#msg145261)  According to the new minister of transport (Razvan Cuc), "all bureaucratic hurdles" regarding the opening of the 15 km A1 section Dumbrava - Margina "have been identified and eliminated" and the motorway will open to traffic in the interval February 6 - 10. [did not happen]
01/20 (http://forum.peundemerg.ro/index.php?topic=2.msg145873#msg145873)  Overview of problems related to A1 sections under construction. Modifying the existing construction contract on section 2 in order to remove sector E (km 47+090 - 56+220) from the scope of works, and then tendering the works on this sector remains the biggest challenge for this year. Additionally, construction permits are still missing for parts of sections 3 and 4, years after the beginning of construction.
01/23 (http://forum.peundemerg.ro/index.php?topic=2.msg145954#msg145954)  Winter pictures from section 4, some taken on a sector where the construction permit still has to be issued.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on February 11, 2017, 08:21:22 PM
January 2017 * A3 Bucharest - Borș

01/21 (http://forum.peundemerg.ro/index.php?topic=6.msg145874#msg145874)  An overview of problems regarding the A3 motorway sections currently under construction or preparation. On the critical path appears to be obtaining the revised environmental permit for the 255 km section west of Târgu Mureș, finalising construction tenders for Râșnov - Cristian, Târgu Mureș - Ungheni and Gilău bridge, as well as retendering the Suplacu de Barcău - Borș section. Additionally, according to NCARI's January monthly report, the intention regarding the 80 km Mihăiești - Suplacu de Barcău sector is to prepare this project for Red FIDIC - a tender is to start in March 2017 to select a consultant for performing detailed design.
01/28 (http://forum.peundemerg.ro/index.php?topic=6.msg146226#msg146226)  Forum members report activity going on west of Târgu Mureș: concrete works (Strabag) and construction camp errection (Geiger), despite sub-zero temperatures.

January 2017 * A7 Ploiești - Bacău - Siret

01/16 (http://forum.peundemerg.ro/index.php?topic=58.msg145600#msg145600)  Winter concrete works on the Bacău bypass.
01/24 (http://forum.peundemerg.ro/index.php?topic=58.msg146007#msg146007)  User rightfully points out the discrepancy between budget allocation for 2017 for the Bacău bypass and a realistic forecast regarding works progress this year.
01/30 (http://forum.peundemerg.ro/index.php?topic=58.msg146302#msg146302)  Submission deadlines for tenders for the revision of FS and preparation of detailed design for the future motorway/expressway A7 between Ploiești and Pașcani, a much awaited project, have been pushed back from early January to mid February.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on February 11, 2017, 08:21:42 PM
January 2017 * A10 Sebeș - Turda

01/03 (http://forum.peundemerg.ro/index.php?topic=165.msg144185#msg144185)  Construction site pictures (though no construction ongoing) from section 2...
01/06 (http://forum.peundemerg.ro/index.php?topic=165.msg144618#msg144618)  ...and section 1.
01/16 (http://forum.peundemerg.ro/index.php?topic=165.msg145639#msg145639)  Overview of current problems on the four construction contracts of A10. The most important appears to be that on section 1 design still needs to be agreed with the contractor for the A1xA10 interchange, as well as for the northernmost 3 km; a revised environmental permit and construction permit will then be issued.
01/21 (http://forum.peundemerg.ro/index.php?topic=165.msg145904#msg145904)  (asp) Forum members report that works are slowly restarting at least on sections 2, 3 and 4...
01/29 (http://forum.peundemerg.ro/index.php?topic=165.msg146268#msg146268)  ...and pics to prove it.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on February 11, 2017, 08:21:59 PM
January 2017 * National roads

01/18 (http://forum.peundemerg.ro/index.php?topic=12.msg145751#msg145751)  The 36 km Rovinari - Bumbești Jiu of DN 66 / E79 road (contract 5R2 of the Roads V rehabilitation programme, in fact retendered - after termination of initial contract - and signed as 5R2A in April 2013) was due for acceptance of works. However this has failed mainly due to some drainage issues identified by the acceptance committee.

January 2017 * Bypasses

01/04 (http://forum.peundemerg.ro/index.php?topic=7.msg144388#msg144388)  Tender for the revision of the FS as well as for preparing detailed design for the Timișoara south/east bypass (between DN 6 eastbound, DN 59 and the southwestern industrial area on DJ 591 - see map here (http://www.zupimages.net/up/17/01/53kb.jpg)) was launched today, deadline for offers submission is April 10. Terms of reference provide for only 6 months for the revision of the FS and 3 months for the detailed design.
01/17 (http://forum.peundemerg.ro/index.php?topic=7.msg145656#msg145656)  A new tender for the revision of FS and detailed design was launched today by NCARI, this time for the Râmnicu Vâlcea bypass. The bypass would serve DN 7 north-south transit traffic, in fact paralleling the A1 Sibiu - Pitești currently under preparation. Additionally, forum members criticise the initial alignment proposal as being too long and curvy.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on April 23, 2017, 04:32:50 PM
February 2017 * Motorways: plans and projects

02/23 (http://forum.peundemerg.ro/index.php?topic=9.msg147586#msg147586)  According to press article, the new minister of transport aims to open to traffic 90 km of motorway in 2017, namely the remainder of the Lugoj - Deva motorway (with the exception of the Holdea - Traian Vuia section comprising the tunnels), sections 3 and 4 of Sebeș - Turda motorway, as well as a 3 km urban section of the Bucharest - Ploiești motorway.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on April 23, 2017, 04:33:12 PM
credits to user TibiV for preparing the Romanian version of this month's A1 digest

February 2017 * A1 Bucharest - Nădlac

02/02 (http://forum.peundemerg.ro/index.php?topic=2.msg146464#msg146464)  According to NCARI's press release, a committee for technical inspection of works is assessing the motorway section Dumbrava - Margina.
02/06 (http://forum.peundemerg.ro/index.php?topic=2.msg146572#msg146572)  NCARI suspends the design contract for updating the feasibility study for the Sibiu - Pitești motorway, for three months. The argument given is that the winter period is inappropriate for geotechnical investigations in the mountain area (however other similar contracts have not seen in the past similar treatment).
02/06 (http://forum.peundemerg.ro/index.php?topic=2.msg146586#msg146586)  Pictures showing reactivation of land slides near Aciliu on Orăștie - Sibiu motorway.
02/13 (http://forum.peundemerg.ro/index.php?topic=2.msg146938#msg146938)  ...and some more pics, showing new faults of hundreds of meters long.
02/15 (http://forum.peundemerg.ro/index.php?topic=2.msg147021#msg147021)  NCARI announces a new technical inspection of the motorway section Dumbrava - Margina, hopefully to be open to traffic soon...
02/17 (http://forum.peundemerg.ro/index.php?topic=2.msg147116#msg147116)  ...however some works still remain to be completed on this section, as shown in this document.
02/21 (http://forum.peundemerg.ro/index.php?topic=2.msg147408#msg147408)  Photo- and video-report from Ilia interchange and section 4 of Lugoj - Deva motorway, no progress in comparison to December 2016 (as expected).
02/22 (http://forum.peundemerg.ro/index.php?topic=2.msg147484#msg147484)  Chart showing monthly progress rates for the three A1 motorway sections under construction.
02/24 (http://forum.peundemerg.ro/index.php?topic=2.msg147644#msg147644)  Ample set of pics from section 3 (Holdea - Grind), showing works taking place at various locations including at the temporary Holdea interchange.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on April 23, 2017, 04:33:30 PM
February 2017 * A3 Bucharest - Borș

02/10 (http://forum.peundemerg.ro/index.php?topic=6.msg146807#msg146807)  Seven bids were submitted for the works tender regarding finalising the construction of the Gilău interchange and Someș bridge. Only when this will be completed, will the A3 section between Gilău and Nădășel (to be finalised this year) be usable for traffic.
02/17 (http://forum.peundemerg.ro/index.php?topic=6.msg147176#msg147176)  First pictures showing on-site activity for the Nădășel - Mihăiești section: archaeology, technological road, construction camp.
02/19 (http://forum.peundemerg.ro/index.php?topic=6.msg147255#msg147255)  Close up pics of structures work on the Ungheni - Ogra section close to Târgu Mureș...
02/22 (http://forum.peundemerg.ro/index.php?topic=6.msg147486#msg147486)  ...that currently stands at 17.2% physical progress and is the only section under construction between Târgu Mureș and Câmpia Turzii.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on April 23, 2017, 04:33:53 PM
February 2017 * A7 Ploiești - Bacău - Siret

02/09 (http://forum.peundemerg.ro/index.php?topic=58.msg146749#msg146749)  Winter works: piling on the Bacău bypass.
02/25 (http://forum.peundemerg.ro/index.php?topic=58.msg147693#msg147693)  And more pics that appear to promise a busy 2017 construction season for this project.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on April 23, 2017, 04:34:18 PM
February 2017 * A10 Sebeș - Turda

02/08 (http://forum.peundemerg.ro/index.php?topic=165.msg146688#msg146688)  Pics showing works slowly restarting on section 2...
02/10 (http://forum.peundemerg.ro/index.php?topic=165.msg146798#msg146798) and 02/12 (http://forum.peundemerg.ro/index.php?topic=165.msg146894#msg146894)  ...as well as section 1.
02/12 (http://forum.peundemerg.ro/index.php?topic=165.msg146909#msg146909)  Section 2 pics, showing a quite remarkable construction rhythm for February.
02/24 (http://forum.peundemerg.ro/index.php?topic=165.msg147630#msg147630)  Pictures showing works at and around the Mureș bridge at Rădești on section 2...
02/25 (http://forum.peundemerg.ro/index.php?topic=165.msg147707#msg147707)  ...as well as other pics from the same section.
02/25 (http://forum.peundemerg.ro/index.php?topic=165.msg147715#msg147715)  And a set of pics showing a more advanced construction status around Aiud.
02/27 (http://forum.peundemerg.ro/index.php?topic=165.msg147813#msg147813)  The design for the Alba Iulia north interchange appears to be approved, to be built in the configuration shown in the pic from this post.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on April 23, 2017, 04:34:55 PM
February 2017 * National roads

02/07 (http://forum.peundemerg.ro/index.php?topic=12.msg146627#msg146627)  NCARI retenders the design for the four-lane widening of DN 7 between Bâldana and Titu. Apparently the previous tender (from December) was unsuccessful because there were no bids submitted, as the focus is on other tenders for major design contracts.
02/25 (http://forum.peundemerg.ro/index.php?topic=12.msg147674#msg147674)  Many pictures (including description) from the rehabilitation of the DN 5 four-lane section south of Bucharest up to Adunații Copăceni.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on April 23, 2017, 04:46:15 PM
March 2017 * Motorways: plans and projects

03/07 (http://forum.peundemerg.ro/index.php?topic=9.msg148407#msg148407)  An overview of the current network of motorways in Romania shows that its length (after the recent opening of another section of A1) is exactly 747.95 km (entirely double carriageway). However, forum member rightfully complains about the absence of a mature project pipeline.
03/07 (http://forum.peundemerg.ro/index.php?topic=9.msg148472#msg148472)  Forum member presents a very brief (partly comparative) analysis about the easiness to bypass various cities / urban areas in Romania. A thorough analysis of this type could be formally developed in the future to prioritise investments regarding urban and periurban road projects.
03/11 (http://forum.peundemerg.ro/index.php?topic=9.msg149102#msg149102)  (and subsequent posts) Another lengthy, heated and interesting discussion about what is the best strategic approach for improving the road connection between Moldova and Transylvania / rest of Europe.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on April 23, 2017, 04:46:46 PM
credits to user TibiV for preparing the Romanian version of this month's A1 digest

March 2017 * A1 Bucharest - Nădlac

03/04 (http://forum.peundemerg.ro/index.php?topic=2.msg148059#msg148059)  Photoreport from the Holdea U/C temporary interchange (see map (http://forum.peundemerg.ro/index.php?topic=2.msg148142#msg148142) and details (http://forum.peundemerg.ro/index.php?topic=2.msg148158#msg148158)) of the Lugoj - Deva motorway.
03/06 (http://forum.peundemerg.ro/index.php?topic=2.msg148299#msg148299)  Motorway Lugoj - Deva, subsection Dumbrava - Margina (~15.5 km) opened to traffic today. The motorway will bypass the town Făget, as well as an at grade crossing of railway line 212 Lugoj - Ilia. Pictures here (http://forum.peundemerg.ro/index.php?topic=2.msg148305#msg148305).
03/06 (http://forum.peundemerg.ro/index.php?topic=2.msg148352#msg148352)  An aerial video from the Margina interchange shows how the two main traffic flows (eastbound A1 -> DN 68A and westbound DN 68 -> A1) intersect in one of the interchange's roundabouts. This situation will persist until at least 2020, when the missing section Margina - Holdea could open to traffic.
03/09 (http://forum.peundemerg.ro/index.php?topic=2.msg148750#msg148750)  A new construction permit (including for works previously executed) was issued today for Lugoj - Deva section 4...
03/14 (http://forum.peundemerg.ro/index.php?topic=2.msg149310#msg149310), 03/14 (http://forum.peundemerg.ro/index.php?topic=2.msg149340#msg149340), 03/15 (http://forum.peundemerg.ro/index.php?topic=2.msg149400#msg149400)  ...and pics to prove that the contractor is back in business on this section.
03/16 (http://forum.peundemerg.ro/index.php?topic=2.msg149490#msg149490), 03/16 (http://forum.peundemerg.ro/index.php?topic=2.msg149495#msg149495), 03/16 (http://forum.peundemerg.ro/index.php?topic=2.msg149521#msg149521), 03/17 (http://forum.peundemerg.ro/index.php?topic=2.msg149733#msg149733)  More pics from the most difficult location on this section - its easternmost sector, close to the Șoimuș interchange, where it will we connect to the existing Deva - Sibiu motorway. The third link includes an aerial rendering of the future motorway; the fourth link discusses the connection with the existing motorway.
03/20 (http://forum.peundemerg.ro/index.php?topic=2.msg149960#msg149960)  An overview of the critical issues affecting construction progress on Lugoj - Deva motorway section 4. Opening to traffic of this section in 2017 is extremely improbable, with a 2018 opening depending on NCARI's assistance in promptly solving the issues described.
03/24 (http://forum.peundemerg.ro/index.php?topic=2.msg150398#msg150398)  Photoreport shows ongoing slide of the Bucium hill near Aciliu on section 3 of the Orăștie - Sibiu motorway.
03/25 (http://forum.peundemerg.ro/index.php?topic=2.msg150477#msg150477)  Pictures from the future Holdea interchange, construction still in early stages.
03/25 (http://forum.peundemerg.ro/index.php?topic=2.msg150497#msg150497), 03/28 (http://forum.peundemerg.ro/index.php?topic=2.msg150795#msg150795), 03/30 (http://forum.peundemerg.ro/index.php?topic=2.msg151031#msg151031)  Construction pics from the Lugoj - Deva motorway section 4. The first covers the entire section from Bretea Mureșeană to Șoimuș, with the second and third addressing the Minția and Șoimuș interchange areas respectively.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on April 23, 2017, 04:47:11 PM
March 2017 * A3 Bucharest - Borș

03/06 (http://forum.peundemerg.ro/index.php?topic=6.msg148230#msg148230)  Aerial video covering location and some works ongoing between the Iernut and Târgu Mureș airport interchanges on the A3.
03/06 (http://forum.peundemerg.ro/index.php?topic=6.msg148243#msg148243)  Despite the motorway Bucharest - Ploiești having been open to traffic since the summer of 2012, its Moara Vlăsiei interchange at DJ 101 (http://www.openstreetmap.org/#map=15/44.6353/26.1923) is still not officially operational.
03/07 (http://forum.peundemerg.ro/index.php?topic=6.msg148459#msg148459)  Bids finally received for the easternmost section (Târgu Mureș - Ungheni) of the Târgu Mureș - Câmpia Turzii motorway.
03/09 (http://forum.peundemerg.ro/index.php?topic=6.msg148768#msg148768)  Map made by forum member showing the most important request of the Cluj county council regarding the proposed Nădășel - Mihăiești section alignment: relocating the planned (red) motorway alignment to the east (green), in order to avoid crossing the Șardu village. This may lead to delays in the construction of this section.
03/11 (http://forum.peundemerg.ro/index.php?topic=6.msg149053#msg149053)  Forum member shares map showing the current situation on the urban section of A3 inside north Bucharest. Blue section is expected to open soon, however much work is still needed for the orange section.
03/12 (http://forum.peundemerg.ro/index.php?topic=6.msg149122#msg149122)  Construction pics prove that the spring has arrived on the Ungheni - Ogra motorway section.
03/14 (http://forum.peundemerg.ro/index.php?topic=6.msg149304#msg149304)  Forum member shares knowledge about test piles as being prepared on the Nădășel - Mihăiești section, as well as future motorway location pictures.
03/14 (http://forum.peundemerg.ro/index.php?topic=6.msg149384#msg149384)  According to the monthly NCARI progress report, the Ungheni - Ogra section has seen between February and March a progress rate of over 3.5% (from 17.2% to 20.8%)...
03/17 (http://forum.peundemerg.ro/index.php?topic=6.msg149681#msg149681)  ...and a pic to support this claim.
03/18 (http://forum.peundemerg.ro/index.php?topic=6.msg149843#msg149843)  More construction pics from the same section.
03/22 (http://forum.peundemerg.ro/index.php?topic=6.msg150273#msg150273) and 03/23 (http://forum.peundemerg.ro/index.php?topic=6.msg150306#msg150306)  And even more pics.
03/24 (http://forum.peundemerg.ro/index.php?topic=6.msg150369#msg150369)  Pics showing that the construction season has started also on section Gilău - Nădășel.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on April 23, 2017, 04:47:27 PM
March 2017 * A7 Ploiești - Bacău - Siret

03/15 (http://forum.peundemerg.ro/index.php?topic=58.msg149399#msg149399)  Contractor of the Bacău bypass shares new construction pics.
03/25 (http://forum.peundemerg.ro/index.php?topic=58.msg150455#msg150455)  Deadline for the submission of bids for the studies for the preparation of the Ploiești - Pașcani motorway/expressway has been again pushed forward, current deadline is April 12.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on April 23, 2017, 04:47:45 PM
March 2017 * A10 Sebeș - Turda

03/01 (http://forum.peundemerg.ro/index.php?topic=165.msg147900#msg147900)  User reports 10-hour working programme has restarted on section 1; pics included.
03/05 (http://forum.peundemerg.ro/index.php?topic=165.msg148176#msg148176)  Pics from the Gâmbaș cut and viaduct, some of the most complex areas on section 3.
03/05 (http://forum.peundemerg.ro/index.php?topic=165.msg148177#msg148177)  Section 2 includes two bridges over the Mureș river, and only a minor part of the works has been completed for these two structures.
03/05 (http://forum.peundemerg.ro/index.php?topic=165.msg148201#msg148201)  Pics from the northern half of section 1, east of Alba Iulia...
03/06 (http://forum.peundemerg.ro/index.php?topic=165.msg148247#msg148247)  ...and some from the southern half.
03/07 (http://forum.peundemerg.ro/index.php?topic=165.msg148518#msg148518)  More construction pics, this time focusing on section 4, including at the A3xA10 interchange.
03/14 (http://forum.peundemerg.ro/index.php?topic=165.msg149319#msg149319)  Construction pics from the southern end of section 2, near Alba Iulia. Following posts feature construction on other sections too.
03/19 (http://forum.peundemerg.ro/index.php?topic=165.msg149872#msg149872)  Panoramic pics from sections 2 and 3 from around Aiud, as well as more pics from neighbouring sectors posted by the same forum member.
03/21 (http://forum.peundemerg.ro/index.php?topic=165.msg150148#msg150148)  Relocation of a "stubborn" power tower on the motorway right of way (section 4), as well as additional land acquisition (section 1) are finally happening.
03/24 (http://forum.peundemerg.ro/index.php?topic=165.msg150357#msg150357)  Pics showing beam installation at the Decea interchange on section 3; forum member reports an outstanding mobilisation on this section.
03/24 (http://forum.peundemerg.ro/index.php?topic=165.msg150370#msg150370) and 03/24 (http://forum.peundemerg.ro/index.php?topic=165.msg150387#msg150387)  Heavy works photodocumented also on section 1; however designs for the end sectors (the A1xA10 Sebeș interchange as well as the Alba Iulia north interchange) still need to be agreed and approved.
03/26 (http://forum.peundemerg.ro/index.php?topic=165.msg150515#msg150515)  More pics from the same section, where from now on Sunday will also be a working day.
03/26 (http://forum.peundemerg.ro/index.php?topic=165.msg150525#msg150525)  Aerial video of the works at the A3xA10 interchange near Turda.
03/26 (http://forum.peundemerg.ro/index.php?topic=165.msg150562#msg150562)  Aerial video of the entire section 3, currently 57.5% completed. First minute of the video is in fact from section 2, south of Aiud...
03/27 (http://forum.peundemerg.ro/index.php?topic=165.msg150593#msg150593)  ...and an aerial video from section 4.
03/28 (http://forum.peundemerg.ro/index.php?topic=165.msg150775#msg150775)  Construction pics from section 1, showing quite a delay when compared to sections 3 and 4.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on April 23, 2017, 04:47:57 PM
March 2017 * National roads

03/09 (http://forum.peundemerg.ro/index.php?topic=12.msg148823#msg148823)  The second tender for the design of the DN 7 Bâldana - Titu widening has been canceled.
03/13 (http://forum.peundemerg.ro/index.php?topic=12.msg149294#msg149294)  Report (includes pics) about restarting of works on the modernisation of DN 18 between Borșa and Iacobeni in the far north.
03/20 (http://forum.peundemerg.ro/index.php?topic=12.msg149969#msg149969)  Forum member reports that the environmental permit procedure has started for the A1 - DN 69 connector expressroad, a highly important periurban road north of Timișoara.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on April 23, 2017, 04:48:10 PM
March 2017 * Bypasses
03/08 (http://forum.peundemerg.ro/index.php?topic=7.msg148616#msg148616)  Link to aerial video of the Târgu Mureș bypass works (video section showing current status starts at 1:20). Works are at 25.7% progress.
03/15 (http://forum.peundemerg.ro/index.php?topic=7.msg149441#msg149441)  It appears that the Satu Mare bypass road project is finally seeing some progress (the D&B contract was signed in November 2015), with the land acquisition government decision issued today.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on May 14, 2017, 03:32:32 PM
April 2017 * Motorways: plans and projects

04/26 (http://forum.peundemerg.ro/index.php?topic=9.msg153530#msg153530)  According to a press release of the prime minister's office, the following large road infrastructure projects should see tenders launched for construction this year: bridge over Danube at Braila ("soon"), expressway Craiova - Pitesti (June 2017), Bucharest motorway bypass A0 southern half (July - August 2017), Sibiu - Pitesti sections 1 and 5 (June - July 2017), Suplacu de Barcau - Bors motorway (July - August 2017).
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on May 14, 2017, 03:32:58 PM
April 2017 * A1 Bucharest - Nădlac

(tbd)
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on May 14, 2017, 03:33:16 PM
April 2017 * A3 Bucharest - Borș

04/02 (http://forum.peundemerg.ro/index.php?topic=6.msg151354#msg151354) and 04/02 (http://forum.peundemerg.ro/index.php?topic=6.msg151441#msg151441)  Construction pics from motorway section Ungheni - Ogra...
04/03 (http://forum.peundemerg.ro/index.php?topic=6.msg151521#msg151521)  ...and a drone aerial video from the same section.
04/06 (http://forum.peundemerg.ro/index.php?topic=6.msg151733#msg151733)  Aerial video from the northern half of the Gilău - Nădășel motorway, nearing completion.
04/13 (http://forum.peundemerg.ro/index.php?topic=6.msg152413#msg152413)  Construction pics from the Bucharest periurban section of A3.
04/17 (http://forum.peundemerg.ro/index.php?topic=6.msg152638#msg152638)  Awaiting for the environmental and construction permits, the contractor from the section Iernut - Chețani has build a temporary technological bridge over the Mures river near Gheja, as seen in the pics in this post.
04/23 (http://forum.peundemerg.ro/index.php?topic=6.msg153087#msg153087)  According to a statement of the minister of transport, the A3 sections west of Cluj will be co-financed from EU funds under this programming period, as part of the LIOP.
04/23 (http://forum.peundemerg.ro/index.php?topic=6.msg153185#msg153185) and 04/25 (http://forum.peundemerg.ro/index.php?topic=6.msg153359#msg153359)  More pics (not so much activity though) from the southern terminus of A3 in Voluntari/Bucharest.
04/26 (http://forum.peundemerg.ro/index.php?topic=6.msg153602#msg153602)  Forum member presents brief analysis of the five construction contracts on the motorway Târgu Mureș - Câmpia Turzii, concluding that realistically the motorway could be fully functional by the end of 2019.
04/26 (http://forum.peundemerg.ro/index.php?topic=6.msg153608#msg153608)  Two new construction permits have been issued for eastern segments of this motorway.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on May 14, 2017, 03:33:32 PM
April 2017 * A7 Ploiești - Bacău - Siret

04/04 (http://forum.peundemerg.ro/index.php?topic=58.msg151628#msg151628)  Despite strong rumours regarding termination of the construction contract for the Bacău bypass, pictures show that works are still ongoing.
04/10 (http://forum.peundemerg.ro/index.php?topic=58.msg152074#msg152074)  Official confirmation from NCARI of having received an intention letter regarding termination of the contract for the construction of the Bacău bypass from the contractor Eko Insaat Ve Tic AS. Contract was signed two years ago (on April 1, 2015), but the project has seen a progress of only 2% during this interval.
04/13 (http://forum.peundemerg.ro/index.php?topic=58.msg152335#msg152335)  Notice of termination of the contract for the construction of the 30.7 km Bacău bypass has been formally submitted by NCARI.
04/16 (http://forum.peundemerg.ro/index.php?topic=58.msg152559#msg152559)  NCARI states that the new tender will include a full motorway profile for the Bacău bypass subsection that is to become a part of the future north-south motorway/expressway in Moldova.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on May 14, 2017, 03:33:52 PM
April 2017 * A10 Sebeș - Turda

04/02 (http://forum.peundemerg.ro/index.php?topic=165.msg151411#msg151411)  Construction pics from sections 1 and 2; mobilisation is rated as disappointing for section 2.
04/05 (http://forum.peundemerg.ro/index.php?topic=165.msg151684#msg151684)  Article linked in this post contains collection of pics showing the extremely close proximity of the future motorway to some houses in Oarda (https://www.google.ro/maps/@46.0238468,23.5771236,3a,75y,43.72h,75t/data=!3m6!1e1!3m4!1sEBlr2EIuleyqvcwkexuDKg!2e0!7i13312!8i6656), close to Alba Iulia.
04/07 (http://forum.peundemerg.ro/index.php?topic=165.msg151908#msg151908)  April construction pics from section 4.
04/08 (http://forum.peundemerg.ro/index.php?topic=165.msg151910#msg151910) 04/08 (http://forum.peundemerg.ro/index.php?topic=165.msg151950#msg151950) 04/09 (http://forum.peundemerg.ro/index.php?topic=165.msg152007#msg152007) 04/09 (http://forum.peundemerg.ro/index.php?topic=165.msg152013#msg152013) 04/14 (http://forum.peundemerg.ro/index.php?topic=165.msg152420#msg152420) 04/29 (http://forum.peundemerg.ro/index.php?topic=165.msg153969#msg153969)  April construction pics from section 3.
04/08 (http://forum.peundemerg.ro/index.php?topic=165.msg151946#msg151946) 04/09 (http://forum.peundemerg.ro/index.php?topic=165.msg151997#msg151997) 04/14 (http://forum.peundemerg.ro/index.php?topic=165.msg152418#msg152418) 04/26 (http://forum.peundemerg.ro/index.php?topic=165.msg153601#msg153601) 04/29 (http://forum.peundemerg.ro/index.php?topic=165.msg153942#msg153942) 04/29 (http://forum.peundemerg.ro/index.php?topic=165.msg153970#msg153970)  April construction pics from section 2.
04/09 (http://forum.peundemerg.ro/index.php?topic=165.msg152042#msg152042) 04/09 (http://forum.peundemerg.ro/index.php?topic=165.msg152048#msg152048) 04/22 (http://forum.peundemerg.ro/index.php?topic=165.msg153036#msg153036) 04/26 (http://forum.peundemerg.ro/index.php?topic=165.msg153594#msg153594) 04/28 (http://forum.peundemerg.ro/index.php?topic=165.msg153859#msg153859) 04/29 (http://forum.peundemerg.ro/index.php?topic=165.msg153976#msg153976)  April construction pics from section 1.
04/09 (http://forum.peundemerg.ro/index.php?topic=165.msg152030#msg152030)  Aerial video from section 2 confirms rather anemic mobilisation.
04/29 (http://forum.peundemerg.ro/index.php?topic=165.msg153943#msg153943)  Aerial pictures covering all four motorway sections.
04/30 (http://forum.peundemerg.ro/index.php?topic=165.msg154002#msg154002)  Aerial video from section 2 shows that the forecast opening date (September 2017) appears to be realistic.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on May 14, 2017, 03:34:13 PM
April 2017 * National roads

04/06 (http://forum.peundemerg.ro/index.php?topic=12.msg151763#msg151763)  It appears that works are finally ramping up on DN 18 between Moisei and Iacobeni, that connects Maramureș and Bucovina in the far north. Article reports that at least for the western half of this road we should have all works finalised this year with the exception of the wearing course.
04/11 (http://forum.peundemerg.ro/index.php?topic=12.msg152233#msg152233)  According to statements of the minister of transport, it also appears that works will continue this year on modernising two north-south roads connecting to the above-mentioned sector of DN 18, namely DN 17C and DN 17D. The article further quotes the minister saying that the GTMP project Turda - Dej - Baia Mare - Halmeu expressway (as well as the branch Dej - Bistrița) will see preparation studies in 2018.
04/26 (http://forum.peundemerg.ro/index.php?topic=12.msg153523#msg153523)  Retender of the modernisation of DN 6 Alexandria - Craiova, section 2 (km 132+435 - km 185+230) has been started today, submission of bids by June 14. This is in fact the second retender of this contract (first retender, unsuccessful, started in December 2013). The initial works contract had been signed in January 2011, and terminated in December 2012.
04/29 (http://forum.peundemerg.ro/index.php?topic=12.msg153966#msg153966)  Dashcam video of DN 1H between Aleșd and Zalău, modernised with ERDF cofinancing under SOP-T 2007 - 2013.
Title: Re: Monthly Road Infrastructure Digest (EN)
Post by: north on May 14, 2017, 03:34:30 PM
April 2017 * Bypasses

04/10 (http://forum.peundemerg.ro/index.php?topic=7.msg152131#msg152131)  Pics showing ongoing works on the construction of the second segment of the Tecuci bypass, connecting DN 24 (west) to DN 25 (south) - see map (http://www.openstreetmap.org/#map=13/45.8449/27.4480).
04/14 (http://forum.peundemerg.ro/index.php?topic=7.msg152378#msg152378)  Forum member rightfully points out that there is no news from the Ministry of Transport / NCARI regarding the abandoned construction sites of the Suceava, Săcuinei and Carei bypasses.
04/19 (http://forum.peundemerg.ro/index.php?topic=7.msg152751#msg152751)  Forum member reports (pics included) that almost nothing has changed on the Târgu Jiu bypass construction site (at least in three critical locations he surveyed) as compared to one year ago.
04/20 (http://forum.peundemerg.ro/index.php?topic=7.msg152894#msg152894)  Forum member reports that works are ongoing at a satisfactory rate at the construction of the Târgu Mureș bypass.
04/23 (http://forum.peundemerg.ro/index.php?topic=152.msg153090#msg153090)  The tender for the design and construction of the Timișoara bypass (from DN 6 east to DJ 591 southwest) was launched today. This will be a 25.6 km 2x1 road (see red alignment of map here (http://i.imgur.com/gSX7m39.jpg)) with mostly grade separated interchanges.
04/27 (http://forum.peundemerg.ro/index.php?topic=152.msg153763#msg153763)  Forum member heavily criticises the government's decision to cancel the tender for the revision of the FS for the Timișoara bypass (that had been launched in January 2017, and which intended to study the preparation of a 2x2 design) and instead tender the D&B on a 2011 FS with 2x1 design. He argues that construction will not in any way finalise before 2020, and that by that time the bypass will already have a poor LOS, most likely seeing congestion from the first days of being open to traffic.
04/24 (http://forum.peundemerg.ro/index.php?topic=7.msg153219#msg153219)  Works are ramping up on the construction of the Mihăilești bypass, a commune on DN 6 some 10 km southwest of Bucharest (http://www.openstreetmap.org/#map=14/44.3189/25.9066).
04/26 (http://forum.peundemerg.ro/index.php?topic=7.msg153522#msg153522)  The much-needed widening of the Bucharest bypass in its eastern part, sector DN 2 (km 12+300) - A2 (km 23+750), was retendered today.